System Installation Checklist
Page A-3
System Installation Checklist
A
System Installation Checklist
The checklist (
) provides a description of the required procedures
numbered in the sequence in which you must complete them. The “Chapter”
and “Section” columns refer you to the appropriate chapter number and section
title of the system installation book.
As you complete a procedure, make a check mark in the “
✔
” column.
Table A-1.
MAP Hardware Installation Checklist — Pre-assembled
System
Task
Task Description
Comments
Chapter
Section
✔
1
Verify site
environmental
requirements.
1
‘‘Environmental
Considerations’’
2
Verify site installation
requirements.
1
‘‘Installation Area
Considerations’’
3
Verify site space
requirements.
1
4
Verify site power
requirements.
1
5
Verify site is prewired
for all pinout
connections.
Required for
telephone lines
and switch
integration
1
Verify with System
Administrator.
6
Review demarcation
points.
All systems,
application
dependent
1
7
Review all safety
warnings before
getting started.
1
‘‘System
Grounding
Connections’’
8
Observe
electrostatic
discharge
guidelines.
Required for all
circuit cards and
peripheral disk
drives
1
‘‘System
Grounding
Connections’’
9
Gather the required
tools.
1
10
Unpack the MAP.
Open as
instructed to reuse
packing materials
2
Continued on next page