INTUITY CONVERSANT System Version 6.0
MAP/100 New System Installation
585-310-176
Issue 3.0
June 1997
Unpacking the MAP/100 and Installing Nonassembled Hardware
Page 2-4
Installing Split Ferrite Core Toroids
2
Figure 2-1.
Split Ferrite Core Toroid Installation
NOTE:
If the MAP/100 monitor is plugged directly into a wall outlet, do not place a
split ferrite core toroid on the power cord.
To install the split ferrite core toroids:
1. Open the split ferrite core toroid by gently pulling the fastener away from
the body of the split ferrite core toroid (
2. Place the power cord in the groove inside a split ferrite core toroid
3. Place the toroid against the female connector which connects to the 110
VAC power input on the back of the MAP/100.
4. Gently snap the split ferrite core toroid shut around the cable (
).
5. Attach a cable tie directly behind the split ferrite core toroid to secure it.
6. Cut and remove the excess cable tie.
7. Place the monitor power cord in the groove inside a split ferrite core toroid
8. Place the toroid against the male connector which connects to the
auxiliary monitor power input on the back of the MAP/100.
Split ferrite core
To map input
Split ferrite core
fastener
Cable tie
(.1 x 8.0 inch)
Mount up tight
against power cord
connector