9.2.4.7 Inspection Criteria
Table 9-1 ICA Inspection Criteria
xVue Touch System
Component Description
Inspection Requirement
Recommended Minimum
Inspection Interval
Completed
KCP 100EXP Control
Panel
A general visual inspection of the KCP
100EXP Control Panel, installation and the
associated wiring must be performed
during each annual inspection. Visually
check wiring for general condition, routing,
chafing, bonding straps and/or wires and
integrity of clamping and stand-offs.
Visually check the mechanical installation
for condition, including checking the unit
and all mounting brackets for security.
Loose and chafing brackets will increase the
resistance between parts. Check for signs
that the units have not been tampered with
or removed. Inspect and verify the bonding
straps or ground wires are in good
condition, and are not loose or chafing.
Connection points to the units and to the
airframe must be inspected for evidence of
corrosion.
If any of these indications are present, an
electrical bonding test must be performed.
12 months
KTP 73 Outside Air
Temperature Probe
A general visual inspection of the KTP 73
Outside Air Temperature Probe and the
associated wiring must be performed
during each annual inspection. Visually
check wiring for general condition, routing,
chafing, bonding straps and/or wires and
integrity of clamping and stand-offs.
Visually check the mechanical installation
for condition, including checking the unit
and all mounting brackets for security.
Loose and chafing brackets will increase the
resistance between parts. Check for signs
that the units have not been tampered with
or removed. Inspect and verify the bonding
straps or ground wires are in good
condition, and are not loose or chafing.
Connection points to the units and to the
airframe must be inspected for evidence of
corrosion.
If any of these indications are present, an
electrical bonding test must be performed.
12 months