Keep the following in mind when selecting a site for your Lift:
•
Architectural plans
. Consult the architectural plans for your desired installation location. Make
sure there are no issues between what you want to do and what the plans show.
•
Enough space
. Make sure there is adequate space on all sides, plus enough room above for the
Vehicles you will be raising. Refer to
•
No overhead obstructions
. Make sure the site is free of low-hanging overhead obstructions.
•
Floor
. Only install the Lift on a flat, Concrete floor; do not install on asphalt or any other surface.
The surface must be level; do not install if the surface has more than three degrees of slope.
⚠
WARNING
Installing your Lift on a surface with more than three degrees of slope could lead to
injury or even death. Only install the Lift on a level floor. If your floor is not level,
considering making the floor level or using a different location.
•
Shimming
. If your Concrete floor is not completely level, you can use Shims under the Base
Plates, as needed, to level the Lift. To estimate your Shim requirements, use a transit level and
targets to check for flatness. Use the provided Shims as necessary.
NOTICE
Do not shim a Base Plate more than half an inch using the provided Shims and Anchor
Bolts. A maximum shim of 2 inches is possible by ordering Shim Plates. Contact
BendPak at
(800) 253–2363
, extension 191 to order.
•
Concrete specifications
. Do not install the Lift on cracked or defective concrete. Make sure
the concrete is at least 4.25 inches thick, 3,000 psi, and cured for at least 28 days (if newly
poured). Make sure the floor is defect-free, dry, and level. Only install the Lift on concrete.
⚠
CAUTION
BendPak Lifts are supplied with installation instructions and Concrete anchors that
meet the criteria set by the current version of the American National Standard
“Automotive Lifts — Safety Requirements for Construction, Testing, and Validation”,
ANSI/ALI/ALCTV. You are responsible for any special regional structural and/or
seismic anchoring requirements specified by any other agencies and/or codes such
as the Uniform Building Code (UBC) and/or International Building Code (IBC).
Be sure to check your Concrete floor for the possibility of it being a
post-tension slab
. In this
case, you must contact the building architect before drilling. Using ground penetrating radar may
help you find the tensioned steel.
•
Power
. You need an appropriate power source near the Console. If you are using the Lift at 220
VAC at 60 Hz,1 Ph, use a 25 amp or greater fuse. For a 380 VAC, use a 15 amp or greater fuse.
•
Operating temperature
. The Lift is designed to be used between temperatures of 41º to 104ºF
(5º to 40ºC).
•
Outdoor installation
. All Lift models are approved for indoor installation and use only. Outdoor
installation is prohibited.
•
Second floor installs
. Do not install your Lift on a second floor or elevated floor without first
consulting the building architect and getting their permission.
•
Dress properly
. Wear protective gear (safety goggles, helmet, heavy gloves, suitable working
clothes, safety boots, ear protection, and so on) at all times when installing the Lift. Do not wear
loose clothing or jewelry; contain long hair; keep hair, clothing, and gloves away from moving parts.
⚠
WARNING
Always wear appropriate protective gear when working on the Lift.
Summary of Contents for Quatra XR-12000L
Page 51: ...Quatra Full Rise Scissor Lift 51 P N 5900085 Rev A1 October 2019 Wiring Diagrams 5585320 ...
Page 52: ...Quatra Full Rise Scissor Lift 52 P N 5900085 Rev A1 October 2019 5585321 ...
Page 53: ...Quatra Full Rise Scissor Lift 53 P N 5900085 Rev A1 October 2019 Labels ...
Page 54: ...Quatra Full Rise Scissor Lift 54 P N 5900085 Rev A1 October 2019 ...
Page 55: ...Quatra Full Rise Scissor Lift 55 P N 5900085 Rev A1 October 2019 Parts Drawings ...
Page 56: ...Quatra Full Rise Scissor Lift 56 P N 5900085 Rev A1 October 2019 ...
Page 57: ...Quatra Full Rise Scissor Lift 57 P N 5900085 Rev A1 October 2019 ...
Page 58: ...Quatra Full Rise Scissor Lift 58 P N 5900085 Rev A1 October 2019 ...
Page 59: ...Quatra Full Rise Scissor Lift 59 P N 5900085 Rev A1 October 2019 ...
Page 60: ...Quatra Full Rise Scissor Lift 60 P N 5900085 Rev A1 October 2019 ...
Page 61: ...Quatra Full Rise Scissor Lift 61 P N 5900085 Rev A1 October 2019 ...
Page 62: ...Quatra Full Rise Scissor Lift 62 P N 5900085 Rev A1 October 2019 ...
Page 63: ...Quatra Full Rise Scissor Lift 63 P N 5900085 Rev A1 October 2019 ...
Page 64: ...Quatra Full Rise Scissor Lift 64 P N 5900085 Rev A1 October 2019 ...
Page 65: ...Quatra Full Rise Scissor Lift 65 P N 5900085 Rev A1 October 2019 ...
Page 66: ...Quatra Full Rise Scissor Lift 66 P N 5900085 Rev A1 October 2019 ...
Page 67: ...Quatra Full Rise Scissor Lift 67 P N 5900085 Rev A1 October 2019 ...
Page 68: ...Quatra Full Rise Scissor Lift 68 P N 5900085 Rev A1 October 2019 ...
Page 69: ...Quatra Full Rise Scissor Lift 69 P N 5900085 Rev A1 October 2019 ...
Page 70: ...Quatra Full Rise Scissor Lift 70 P N 5900085 Rev A1 October 2019 Maintenance Log ...
Page 71: ...Quatra Full Rise Scissor Lift 71 P N 5900085 Rev A1 October 2019 Maintenance Log ...