GENERAL INSTRUCTIONS

Adjustment of burner

The burner is from the factory pre-set 
to an average value that must then be 

adjusted to the boiler in question.

All burner adjustments must be made 

in accordance with boiler manu-facturers 
instructions. These must include the 

checking  of  flue  gas  temperatures, 

average water temperature and CO

2

 

or O

2

 concentration.

General instructions

The installation of the gas burner 
must be carried out in accordance 
with current regulations and standards. 
The installers of gas burners should 
therefore be acquainted with all regu-
lations and ensure that the installation 
complies with the requirements. The 

installation, mounting and adjustment 

should be made with the greatest 
care and only the correct gas should 
be used.

Operating instructions

The operating instructions accom-
panying the burner should be left 
in a prominent position in the boiler 
room.

Instructions

The user should be thoroughly  
instructed in the function of the gas 
burner and the whole installation. 
The supplier must instruct the user.

Inspection and maintenance

Daily inspection is advisable.

Start up

After  the  burner  has  been  fitted  to 

the boiler and the electric connection, 
the leakage control, the venting and 
the electric function test have been 
carried out, the burner will be ready 
for start-up.

Howerer, study the sections dealing 

with adjustments of multi-bloc, com

-

bustion air and combustion head.
Open the ball valve and switch on the 
main switch. If the burner starts the 

actual adjustment can be made.

Adjustment of burner head

The burner is equipped with an adjust

-

ment device changing the po si tion of 
the brake plate in the burner head. This 

is used to adjust the cor rect pressure 

drop over the com bus tion device in 
order to obtain a good pulsation free 
combustion. 

Which position to use depends on 
input and overpressure in the boiler.

172 305 28  07-01

A general rule is that the lower capacity 
the smaller the opening between 
brake plate and combustion device.

Commissioning of installation

Control of the combustion. The com-
bustion quality is checked by means 

of a flue gas analysis device. Adjust 

the burner to appr. 20% excess air 

in accordance with the table. Check 

the flue gas temperature. Calculate 

the efficiency. Check also the actual 

gas volume on the gas meter so that 
the correct input is achieved.

Service

Service should only be carried out 

by qualified personnel. Replacement 

parts should be of the same make and 
approved by the same authorities as 
the original. If the burner is converted 

to fire another gas quality it must be 

re-commissioned. If town gas is to be 

fired the combustion head must be 

converted and the gas train adjusted 

to suit (e.g.a larger gas armature or a 
different spring in the governor may 
be required).

Gas quality

CO

2

 

lambda 1,2

0

2

%

max. CO

2

%

Natural gas

10,0

3,5

11,9

LPG

11,5

3,5

13,9

Summary of Contents for BG 450 M

Page 1: ...178 016 76 Installation and maintenance instruction BG450M...

Page 2: ...op is installed before servicing Take great care when servicing Trap and pinch risks can be present The boiler s sound level can exceed 85 dBA during operation Use ear protectors when present in the b...

Page 3: ...0 Motor 18 Switch l ll For modulating burner Change over switch manually automatically 19 Indicating lamp Stage 1 20 Switch 0 1 21 Contactor 22 Control box 23 Ignition transformer 24 MultiBloc 11 Conn...

Page 4: ...mbar mbar Natural gas LPG Natural gas LPG Natural gas LPG Natural gas LPG 450 120 550 12 4 6 55 21 360 40 30 50 2 Town gas 2 Town gas 2 Town gas 2 Town gas Out range TECHNICAL DATA Type designation BG...

Page 5: ...TECHNICAL DATA DIMENSIONS OF FLANGE 172 215 19 08 01...

Page 6: ...tion is required this valve is equipped with controls for variable opening 6 6 b Safety valve 1 7 Valve proving system 8 Air damper motor 9 Air pressure switch 10 Gas burner control Pos 5b 7 Component...

Page 7: ...s are very useful Do like this Remove the cover of the fan hous ing Loosen the nut D of the gas assembly package Loosen ignition cable and ionisation cable of gas assembly Loosen the screw A on both s...

Page 8: ...1N 50 60 H z 230 V 172 425 61 08 01 ELECTRIC EQUIPMENT Gas burner control LMG22 LME22 Wiring diagram 1 5 If there is no Plug in contact X4 X16 on the boiler connect to the contact enclosed...

Page 9: ...egulations Function 1 Operating switch ON Thermostat ON Gas pressure switch ON Air damper closed A control is made that the air pressure switch does not indicate fan pressure Then the burner motor sta...

Page 10: ...e at the end of TSA Fault or soiled detector electrode Fault or soiled fuel valves Poor adjustment of burner 3 x Air pressure monitor does not close LP faulty LP incorrectly adjusted Fan motor does no...

Page 11: ...n LME 11 permits a maximum of three start attempts if the start cycle is uninterrupted Continuous Off Red Yellow Green 4 5 Colour code table for multi coloured signal lamps Light diodes Status Colour...

Page 12: ...necting signal amplifier Alarm control table Red flashing code on signal lamp LED Possible causes Flashing 2 x No flame at End of TSA Defective or obscured flame monitor Defective or obscured fuel val...

Page 13: ...that phase and neutral are not reversed The gas shut off cock should be closed To prevent the gas pressure switch from locking out it should be linked temporarily After the main switch has been switc...

Page 14: ...MEASURES AND CHECKS BEFORE START UP Inner assembly Town gas Inner assembly Natural gas LPG Inner assembly Biogas UV detector Propan Natural gas 172 205 18 08 01...

Page 15: ...Net calorific value Gas quality kWh Nm3 kJ Nm3 kcal Nm3 Natural gas 10 3 37 144 8 865 Propane 26 0 93 647 22 350 Butane 34 3 123 571 29 492 Town gas 4 9 17 653 4 213 Bio gas 7 0 25 219 6 019 V Gas vol...

Page 16: ...room 172 205 70 07 01 LOC 1 Electrical connection gas pressure switch mini 2 Electrical connection gas valve 3 Pressure switch mini 4 Flange connection inlet 5 Test point connection 1 8 before V1 6 F...

Page 17: ...PBR are ready from factory Mounting instruction impulse lines PL PF and PBr Max inlet pressure 360 mbar Valves V1 V2 class A group 2 in accordance with EN 161 Governor class A group 2 in accordance wi...

Page 18: ...Releasing button By pressing the button and snap ping it down the motor will be released and the damper can easily be turned This function facilitates an exchange of damper motor Start the burner obse...

Page 19: ...udy the sections dealing with adjustments of multi bloc com bustion air and combustion head Open the ball valve and switch on the main switch If the burner starts the actual adjustment can be made Adj...

Page 20: ...e at which the gas switch should switch off Set this pressure by means of the valve Carefully turn the knob see figure until the gas pressure switch switches off The value shown on the scale should th...

Page 21: ...oubles Trouble free operation is dependent onthreefactors electricity gasandair supply Should there be any changes intheratiobetweenthesethreefactors there is a risk of break downs It has been proved...

Page 22: ...nt 5 Is the gas relay of the burner ready for start and not locked out 6 Is the air supply to the burner sufficient To facilitate fault location we have drawn up a scheme showing the most frequent fau...

Page 23: ...t No electrical connection through the air pressure switch Test the adjustment and the function of the air pressure switch The starting load is not correctly adjusted Reduce or increase the gas supply...

Page 24: ...odes are wrongly adjusted Readjust The gas pressure is too high Check and adjust by means of a pressure gauge and a pressure adjustment valve The flue gas side is blocked Check the chimney flue Pulsat...

Page 25: ...high The CO content is too high Excess air when using natural gas and gasoil propane butane Choke the air Air shortage Open the air supply Check the flue gas damper The holes in the gas nozzle are clo...

Page 26: ...BG800 BG800LN and BG950 all fan gas burners to which this declaration relates is in conformity with the following standard s or the normative socument s title and or number and date of issue of the s...