Sheathing Layout for 16' Building

Sheathing

1x4 Trim

Corner Trim

Detail C

Rafter

!

!

!

Cut roof sheathing to fit.

flush

Install the first 4x8 roof sheathing panel against the back of the siding. Note: Install the top edge
of the bottom roof sheathing flush with the face of the 1x4 fascia. See Detail 'C'.

48"x96"

48"x96"

16"x96"

16"x48"

16"x48"

Cut roof sheathing per the appropriate layout below for your shed size. Install roof sheathing
with 7d sinkers, space nails 12" apart. When installing sheathing across the top, insert a
plyclip into the roof sheathing between each truss. There will be a 1" space from top of
roof sheathing and roof peak.

Plyclip

1. Install 71-3/4" long 1x3 door trim on each side of

door frame. Temporarily tack trim flush with door
opening and bottom of siding so they can be
adjusted, if necessary, when installing the doors.

2. Install 71-1/2" long 1x3 on top of door side trim.

3. Install 75-7/8" long 1x4 corner trim on corners of

the sidewalls.

1x4 Corner Trim

Sheathing Layout for 10' or 12' Building

48"x96"

16"x96"

Step 14  

Install Roof Sheathing

Step 13 

Install Corner & Door Trim

Summary of Contents for Cypress

Page 1: ...reenville PA 16125 724 646 3775 This manual is copyrighted Under the copyright laws this manual may not be copied in whole or in part without consent from Reynolds Building Systems Inc Copyright 2010 Revised June 25 2012 Assembly Book the Cypress Door Installed on Side ...

Page 2: ...ptional floor package if ordered will be supplied by a local supplier Our kit does not include the shingles the quantity needed is listed on the back page The siding is primed You will need to apply a finish coat using latex acrylic paint Our framing lumber is imported to provide you the highest quality available However if you need to replace any lumber for any reason please do so and we will rei...

Page 3: ...llows before nailing the flooring measure the floor diagonally corner to corner Then measure the opposite corners These measurements will be the same if the floor is square To keep the 2x4 frame from moving toenail frame to the 4x4 runners Material Description 10 x 8 shed 10 x 10 shed 10 x 12 shed 10 x 16 shed 2x4 Joist Headers 2 pcs 8 2 pcs 10 2 pcs 12 2 pcs 16 2x4 Floor Joist 7 pcs 10 9 pcs 10 1...

Page 4: ...n each end of the stud LAP Edge Siding Extends 3 4 Below Plate LAP Edge Siding Extends 3 1 2 Past Frame 2x4 Bottom Plate IMPORTANT Install all siding extending 3 4 below the bottom plate Tip Use a 3 4 trim board as a gauge Cut Edge Tongue Edge 6 Set aside remaining siding for the front wall 1 Depending on your building length cut 2 two 2x4 boards to the length shown below 8 Shed 89 long 10 Shed 11...

Page 5: ...lue between 2x4s and gusset Nail the gusset to the 2x4s with 12 twelve 6d common nails Angle nails slightly so nails do not protrude through the 2x4s 6 Temporarily screw 2 two 2x4 blocks along the top of 2x4 rafters This will help with the assembly of other gable and the trusses To aid in the assembly of the sidewalls attach 2x4 packing blocks to your floor with 2 1 2 screws This will trap the per...

Page 6: ... assemble 3 three more Four 4 more for a 12 building and 6 six more for a 16 long building 1x3 Collar Tie Before removing sidewall and rafter blocks assemble the roof trusses Step 4 Install Gable on Sidewall 1 Screw 2x4 Block 1 Remove the 2x4 blocks that were used as a guide at the top of rafters Place a gable assembly on back wall with the gusset facing downward towards the floor Place a 2x4 bloc...

Page 7: ...8 siding panel in the center and the panel labeled BR last 4 The siding needs to extend above the top of the wall frame to receive the roof sheathing when installed later Mark and cut the siding above the 2x4 gable frame the thickness of the roof sheathing See detail below Step 5 Apply Siding on Sidewalls FR BL BR FL 3 6 36 3 4 2x4 Gable Frame Cut Siding 1 2 Above Frame 5 Install the siding panel ...

Page 8: ... flush with the side of the door opening and the height to 71 Install another siding panel on the other side of the door opening 5 Install the last siding panel It will extend 3 1 2 past the wall frame If assembling a 10 shed use the 24 siding panel If you are installing the optional window cut an 18 3 8 x 27 1 4 opening 36 from the bottom of the siding 1 Depending on your building length cut 2 tw...

Page 9: ...2x4 boards to the length shown below 8 Shed 89 long 12 Shed 137 long 16 Shed 185 long 2 Install 72 long wall studs between the wall plates per layout below 3 Install 69 1 2 long door jacks with 67 1 2 long 2x3 door header with above 64 1 2 Door Opening 69 1 2 Door Jacks 19 3 4 19 3 4 36 1 4 64 1 2 Door Opening 19 3 4 19 3 4 60 1 4 24 69 1 2 Door Jacks 24 36 1 4 60 1 4 12 1 4 for 8 Building ...

Page 10: ...f the door opening 3 Install the last siding pane It will extend 3 1 2 past the wall frame If assembling a 12 shed use the 24 siding panel If you are installing the optional window cut an 18 3 8 x 27 1 4 opening 36 from the bottom of the siding Note On a 12 long building there will not be enough space to install the wood shutters 1 Install wall panels Secure wall panels together at the corners wit...

Page 11: ...truss using 1 one 1 1 4 wood screw Secure truss to top plate using a 2 1 2 wood screw 2 Install the remaining trusses over the wall studs When installed correctly there will be 22 1 2 between the trusses 21 3 4 22 1 2 Install 65 5 8 long 1x4 gable trim on the sidewalls flush with the top of the siding Use 8d galv nails Step 9 Install Trusses 1x4 Gable Trim ...

Page 12: ...een front and back gable trim Use 8d galv nails 2 Repeat for the back wall 3 Install 4 four 75 long 1x3 trim on corners of front and back walls Install trim flush with the siding on the sidewalls Step 11 Install 2x3 Overhang Install 48 long 2x3 boards on the front and back walls Allow a 3 8 gap between the end of board and back of gable trim Use 10d sinkers Straight Edge Straight Edge 1x4 Fascia ...

Page 13: ... space nails 12 apart When installing sheathing across the top insert a plyclip into the roof sheathing between each truss There will be a 1 space from top of roof sheathing and roof peak Plyclip 1 Install 71 3 4 long 1x3 door trim on each side of door frame Temporarily tack trim flush with door opening and bottom of siding so they can be adjusted if necessary when installing the doors 2 Install 7...

Page 14: ... Tip Paint the siding and the door frames before you attach the siding to the door It will be easier to paint the door frame before the siding is applied Seal the bottom edges of the siding and door frames If the bottom of the doors are in close vicinity to the ground or ramp they will absorbed moisture and rot 5 Lay doors on level surface with the trim facing up Install hinges to the left side of...

Page 15: ...or Stop Barrel Bolt on the back of left door Install metal roof edge the perimeter of the building Install shingles according to the instructions on the wrapper If you need more detailed instructions on installing shingles there are good publications at book stores or newsstands Ridge vent provides ideal ventilation pre venting heat or moisture from damaging your building or its contents Install O...

Page 16: ... Gable Studs 16 3 4 2 1x3 Door Trim 72 8 Blocks for truss jig 12 1 1x3 Door Trim 71 3 4 3 1x3 Truss Collar Tie 72 4 Sidewall Overhang 48 3 6 5 Door Hinges 2 32 x 72 Barn Doors lb 10d Sinkers 2 6 Barrel Bolts 1 Pre built 67 1 2 Door Header 2 lb 8d Galv Nails 1 Door Latch 2 lb 7d Sinkers 48 Hinge Screws 8 Wood Truss Gussets 7 x 12 2 lb 6d Common 36 2 1 2 crews 1 Bottle Wood Glue 96 1 Screws 1 Tube C...