ASSEMBLY
9
ASSEMBLY FOR FRONT STABILIZER
ASSEMBLY FOR SLIDE TRACK
A
B
C
F28
C1
B1
C1
N1
N13
N14
R14
N7
A
N15
N17
N4
LEVELING
THE MACHINE
N13
Secure the front stabilizer(B) to
the main frame(A) using two screw(N4),
two spring washer(N17) and
two washer(N15).
Set the moving roller(F28) on the slide
track(C). Then, secure the slide track to the
main frame(A) using two screws(N1),
two screws(N7), four spring washers(N13) and
four washers(N14).
After the assembly of Figure 1 &
Figure 2, if the machine feels rocky or is not stable,
adjust (B1,C1) to level the machine to achieve stability