6
Choosing a Site
The first step in installing the scale is to choose an appropriate site. Pertinent steps in choosing the site are:
Ensure that the site has adequate approaching / exiting distance to comply with state and local Weights
and Measures regulations. Scale length and scale elevation (maximum fall per foot allowance) will
impact the total area requirement.
The site selected must meet state and local requirements. The following is taken directly from Handbook 44
(H-44) issued by the National Institute of Standards and Technology.
UR.2.6. Approaches
UR.2.6.1., Vehicle Scales - On the approach end or ends of a vehicle scale installed in any one
location for a period of six months or more, there shall be a straight approach as follows:
(a) The width at least the width of the platform, and
(b) the length at least one-half the length of the platform but not required to be more than 40 feet, and
(c) not less than 10 feet of any approach adjacent to the platform shall be constructed of concrete or
similar durable material to insure that this portion remains smooth and level and in the same plane
as the platform. However, rating of sufficient strength to with stand all loads equal to the sectional
capacity of the scale may be installed in this portion. Any slope in the remaining portion of the
approach shall insure, 1) ease of vehicle access, 2) ease for testing purposes, and 3) drainage
away from the scale.
The scale drawings provided meet part (a) of this requirement. The site must be located to meet parts (b) and (c).
The site should have adequate room for trucks to properly align with the platform before pulling on. This is
especially important if trucks must turn before driving onto the scale.
Trucks should remain on the scale for a period of time no longer than is necessary for obtaining the vehicle
weight. Drivers / passengers / pedestrians should not exit their vehicles or use the scale platform as a walkway.
Some jurisdictions require that the scale platform be clearly visible from the location of the scale instrument.
Others will allow the use of closed circuit TV or even a voice intercom. Obtain official approval before starting
construction.
• Check all state and local Weights and Measures requirements before breaking ground to ensure compliance
with all regulations.
• Obtain all necessary permits for construction.
• Check all public utilities to ensure that your site is free of underground lines, pipes or hoses.
• Have assurance that the soil at the site is capable of withstanding a minimum pressure of 3,000 psf or as
specified on the B-TEK, Inc. drawing / print.
• Make sure the site does not intersect existing drains or utilities.
• All surrounding areas must drain away from the scale site.
• Ensure that all overhead objects (i.e. power lines, lights) do not interfere with unloading and setting the scale
modules with a crane.
Summary of Contents for BTEK BS-FECD-P-CPD-M
Page 1: ...BS FESD P CPR M BS FESD P CPD M BS FECD P CPR M BS FECD P CPD M Models Include ...
Page 2: ...www B TEK com 2016 Pit Type Truck Scale Installation Manual 2 ...
Page 22: ...www B TEK com 2016 Pit Type Truck Scale Installation Manual 22 See larger drawing in packet ...
Page 23: ...2016 www B TEK com Pit Type Truck Scale Installation Manual 23 See larger drawing in packet ...