background image

© Biotage 2022

Biotage

®

 Extrahera

 HV-5000 Installation and Familiarization Checklist | Page 1

The following document will ensure that the installation is 
complete and that all installation steps and tasks have been 
performed. It will also provide guidelines for best practices 
and  familiarization of the system after installation has been 
completed. The familiarization is intended to give the system 
operators a basic overview of the operation and maintenance of 
the new instrument, system, and software. Familiarization is not 
intended or designed to substitute a full operator training course. 
Familiarization will take up to a maximum of two hours. 

We cannot guarantee a complete installation or demonstration 
if the site requirements are not met. If you have any questions, 
please do not hesitate to contact your local Biotage

®

 1-Point 

Support

 group.

Please use the checklist below to track progress of both the 
installation and familiarization and fill out this form electroni-
cally. A printed copy should be signed by both the Field Service 
Engineer and Customer and given to the Customer after 
completion.

Installation Checklist

Shipping Review

Tasks

Notes

Inspect the shipment carefully and verify that entire order has 

been received.

Use the packing lists to confirm that no items are missing. Inspect 

for any damages due to shipping. If the packaging or the instrument 

has been damaged, confirm with the customer that the receipt of 

Instrument document was completed and that a claim was initiated 

with the shipping company.

Inspect the shipping containers for damage and review 

contents for internal damage.

Site Preparations

Tasks

Notes

Ensure that the site requirements are met and that the final 

instrument location is accessible and ready for installation.

If available, review the site preparation checklist document signed by 

the Customer.

Ensure that N

2

 gas is present at a pressure of 6 +/- 0.2 Bar.  

Other inert gas option may be chosen.

Ensure that Air is present at a pressure of 6 +/- 0.2 Bar with 

flowrate at 5 L/min
Ensure that the N

2

 gas fulfils the quality required according to 

ISO 8573-1, classification 1-6-1. Indicate if not used. 

If the gas applied is not according to class x-6-x, an air dryer needs to 

be ordered separately (P/N 416441SP).

Biotage

®

 Extrahera

 HV-5000 Installation 

and Familiarization Checklist

Reviews: