28
Installation Manual: BIPV Modules
27
Installation Manual: BIPV Modules
4�1 Transportation in Packaging
• Please observe the personnel requirements pursuant to Chapter
„Responsibility“
.
• Please observe the handling instructions on the packaging.
4�2 Transportation of Individual Modules
Unprotected glass rim on the lower edge of the module.
Risk of damage to module!
• Do not set the module down on its glass rim.
• Leave the module in its original packaging until immediately prior to insertion into the PV array.
• Never hold or carry the module under any circumstances by its connection cables or junction box.
5�1 Checking the Requirements
5�1�1 Roof Plan and String Plan
Ensure that a roof plan and a string plan are supplied which contain at least the following information:
• Description of the system as well as of the snow and wind load assumed for the system
• Positioning of the PV array within the roof area
• Positioning, number and type of mounting clamps
• Specification of all module mounting pitches measured from a reference point
• Division of the PV array into strings
• Grounding and lightning protection cables
5�1�2 Limit of Application
Deviation of actual conditions from the values used in the design. Deadly danger!
Check whether the limit of use the parameters stated in the project documentation (location, roof pitch, building height, wind
and snow load area) correspond to the current buildings, see also section “Technical data / Limit of application”.
• Make sure that the roof lining meets the requirements of protection against rain or waterproofness, depending on the slope
of the roof.
• Observe local roofing regulations or country-specific ventilation regulations.
5�1�3 Safety at Work
• Ensure that the roof is protected by collective protection (scaffolding, roof railings) in accordance with local regulations.
• Ensure that all personnel are equipped with personal protective equipment (PPE) in accordance with legal regulations and
use it correctly.
• Ensure that support staff are properly trained and supervised throughout the work process.
4 TRANSPORTATION
5 INSTALLATION