Operation Sequence
Figure 3
Refer to Figure 3 for the location of switches and controls identified in this
procedure.
1.
Complete the Operation/Maintenance Checklist (pages 12-13).
2.
Place the transmission control lever in the neutral (center) position.
3.
Follow the startup procedures in on page 16, as appropriate.
4.
Pull the throttle to the wide open position.
5.
Push the transmission lever forward for forward motion and backward for
reverse motion.
6.
Start the machine moving forward and slowly open the shot valve. The slower
the machine travels while the shot valve is open, the deeper the profile.
7.
When coming to the end of a pass, close the shot valve about five feet before
stopping. This will allow you to clear the housing of shot keeping you from
blasting a hole when you come to a complete stop.
18
Throttle
Transmission
Control
Shot Valve
Control
Open / Close
Blast Head
Raise / Lower
Always blast in a forward direction.
The dust container of the dust collector must be emptied regularly.
Comply with your local waste treatment regulations considering the
removed material.
Summary of Contents for 1-16DB4-V2
Page 1: ...SERVICE MANUAL 1 16 DB4 V2 VERSION 1 1 www blastrac com 1 800 256 3440...
Page 36: ...Check for leaks after starting theengine...
Page 38: ...35...
Page 40: ...36...
Page 42: ...37...
Page 44: ...38...
Page 46: ...39...
Page 50: ...BLASTRAC RS IN SURFACE PREPARATION Figure 12 43...
Page 57: ...BLASTRAC VATORS IN SURFACE PREPARATION Blast Head Assembly Figure 14 48...