background image

TECHNICAL MAINTENANCE

DISCONNECT THE UNIT FROM POWER SUPPLY BEFORE ANY MAINTENANCE 

OPERATIONS!

MAKE SURE THE UNIT IS DISCONNECTED FROM POWER MAINS BEFORE REMOVING 

THE PROTECTION

Technical maintenance and repair of the fan may commence only after its disconnection from the power mains and after all rotating 
parts are at a complete standstill. Prior to commencing any technical maintenance put up a prohibitory sign on the fan starting panel: 
«Do not switch on! Men at work!» The technical maintenance includes periodic cleaning of the surfaces from accumulated dust and 
dirt.
Technical maintenance must be carried out at least once a year. 
•  Check the grounding screw terminals and electric connectors for proper tightness and tighten them up if necessary.
•  Check the fastening screws for tightness and tighten them up if necessary.
•  Check the bolt connecting the motor shaft to the hub for proper tightness and tighten it up if necessary.
•  Check the fan impeller for contamination and clean it up if necessary. To clean the impeller, the outer lining segment must be 

removed.

Cut off power supply when doing work related to the safety of maintenance. Other work related to electrical characteristics must be 
performed with the power supplied.

AVOID LIQUID SPILLS ON THE MOTOR! DO NOT USE AGGRESSIVE SOLVENTS AND 

SHARP OBJECTS FOR CLEANING!

PRIOR TO COMMENCING ANY TECHNICAL MAINTENANCE PUT UP A PROHIBITORY 

SIGN ON THE FAN STARTING PANEL: 

“DO NOT SWITCH ON! MEN AT WORK!”

POSSIBLE MALFUNCTIONS AND THEIR ELIMINATION

Problem

Possible reasons

Elimination

The fan will not start.

No power supply.

Check the mains switch. Check the electrical connections 

against the wiring diagram. 

Jammed motor.

Carefully check the fan impeller for possible seizure and 

eliminate it, if necessary. If the impeller is in order, replace 

the electric motor. 

The switching equipment 

activates upon fan start-up.

Short circuit in the fan or the electric circuit between 

the fan and the switching equipment.

Eliminate the cause of a short circuit. 

Excessive current consumption due to an overload in 

the electric mains.

Eliminate the cause of excessive current consumption. 

Improper fan starting method. 

Use a soft starter or frequency converter to start the motor 

(see "Asynchronous Electric Motor Starting Methods" 

in the "Connection to power mains" section)

Improper switching equipment.

Re-select the switching equipment in accordance with the 

current regulations and equipment specifications. 

The installed switching equipment is of poor quality 

or its actual performance falls short of the rated values 

stated by the manufacturer.

Re-select the switching equipment by choosing a unit 

which successfully passed commutation and load tests 

and has a technical compliance certificate. The selection 

should be limited to the top five foreign switching 

equipment manufacturers. 

www.blaubergventilatoren.de

tower-sV-k2

14

Summary of Contents for Tower-SV-K2

Page 1: ...Roof mounted centrifugal smoke extraction fan USER S MANUAL EN Tower SV K2...

Page 2: ...al and national construction electrical and technical norms and standards must be observed when installing and operating the unit Disconnect the unit from the power supply prior to any connection serv...

Page 3: ...ck of experience and knowledge unless they have been given supervision or instruction concerning use of the unit by a person responsible for their safety Children should be supervised to ensure that t...

Page 4: ...nditions The fan handles smoke and air mixtures with temperatures up to 600 C for 60 minutes A characteristic feature of Tower SV K2 roof fans is an impeller with backward curved blades and an electri...

Page 5: ...U1 temperate climate HL1 cold climate T1 tropical climate M1 marine moderately cold climate Options K with a terminal box S1 built in external switch 1 5 motor power kW Motor phase and operation mode...

Page 6: ...0 75 2 15 910 8500 Tower SV K2 560 4D 3 X XX 600 2 XXX 3 0 6 48 1420 13000 Tower SV K2 630 8D 0 75 X XX 600 2 XXX 0 75 2 64 700 9000 Tower SV K2 630 6D 1 5 X XX 600 2 XXX 1 50 3 84 940 12500 Tower SV...

Page 7: ...Overall dimensions B A C H d 4 holes www blaubergventilatoren de Tower SV K2 7...

Page 8: ...0 75 K U1 600 2 Zn 1060 1010 750 1121 16 Tower SV K2 630 6D 1 5 K U1 600 2 Zn Tower SV K2 630 4D 5 5 K U1 600 2 Zn Tower SV K2 710 8D 1 1 K U1 600 2 Zn 1105 1180 980 1257 16 Tower SV K2 710 6D 2 2 K U...

Page 9: ...m the fan The fan delivery set may include a mounting frame available separately Install the mounting frame on a load carrying roof section true vertical inside a prepared opening The opening size mus...

Page 10: ...nal box located on the outer casing of the fan impeller located inside the support panel The motor with the impeller is rigidly fixed to the support panel Welded sheet steel construction The hub and c...

Page 11: ...gth and installation method Connection of the unit to the fixed power supply network must be carried out in accordance with the current regulations Caution The type of electrical connection is indicat...

Page 12: ...oth out the inrush the high startup torque has no adverse effects on the operation of the driven mechanism Soft start SS starting A soft starter gradually increases the voltage supplied to the motor f...

Page 13: ...ain relays and contactors go off and the supply generator shuts down Solution In the best case scenario an SS device may help reduce the in rush current to 250 of the motor rated current If this is in...

Page 14: ...OR TO COMMENCING ANY TECHNICAL MAINTENANCE PUT UP A PROHIBITORY SIGN ON THE FAN STARTING PANEL DO NOT SWITCH ON MEN AT WORK POSSIBLE MALFUNCTIONS AND THEIR ELIMINATION Problem Possible reasons Elimina...

Page 15: ...ace the fan with a unit of proper standard size The fan supplies less air than expected Wrong calculation of the ventilation network and wrong selection of the fan Re calculate the network parameters...

Page 16: ...ndling requirements applicable for the particular type of cargo The unit can be carried in the original packaging by any mode of transport provided proper protection against precipitation and mechanic...

Page 17: ...nation of faults in the unit operation to ensure its intended use by the user within the guaranteed period of operation The faults are eliminated by means of replacement or repair of the unit componen...

Page 18: ...www blaubergventilatoren de Tower SV K2 18...

Page 19: ...____________ is installed pursuant to the requirements stated in the present user s manual Installation Stamp Company name Address Phone Number Installation Technician s Full Name Installation Date Si...

Page 20: ...www blaubergventilatoren de B81 1EN 01...

Reviews: