Blue Sky Network
June 2019
Page | 22
HE7200A-BB2327 Install Guide
P/N: 200804
Ground Test & Operational Flight Check Procedures
A functional ground test procedure and an operational flight check procedure should be used to verify
proper installation and functional performance. In order to accomplish a quick functionality check (after
installation is completed), position the aircraft outside of the hangar with no overhead obstructions. With
all other aircraft systems powered down, apply aircraft power to the HE7200A-BB2327 modem unit.
1. Switch the HE7200A-BB2327 power on.
2.
Observe the LED’s. When power is first applied to the HE7200A, all three LED’s will
be on and solid for 2 seconds. Then, the GNSS
and Iridium LED’s will turn off. At this
point the device has passed the boot stage.
3. Allow a couple of minutes to acquire both Iridium and GNSS signal. The respective
LED’s will light upon sufficient signal. Solid green indicates full signal.
4.
Please refer to the “SkyRouter User Guide” for operation & configuration. A
SkyRouter administrator or an authorized SkyRouter mobile app user should verify
that position reports are being received and that the location is accurate.
If any difficulty is experienced with the functionality or operational performance of the HE7200A, please
contact Blue Sky Network for assistance.
The required logbook entries and FAA approvals are the responsibility of the installer and Blue
Sky Network assumes no responsibility for either obligation
.