Blue Sky Energy - Solar Boost 1524iX
9
¾
CAUTION:
A multi-controller system requires the following specialized installation and setup:
1) Each controller must connect to and charge the same primary battery.
2) One controller must be set to address 0 (zero, Master) and the others be set to addresses 1 – 7 with no controllers set the same.
3) Charge parameters are set in the master only.
4) While outputs connect in parallel to a common battery, PV inputs and wiring to each controller must be completely separate.
5) All controllers must be connected to the IPN network as shown in Figure 5.
IPN NETWORK WIRING
FIGURE 5
IPN Network Address – DIP’s #1, #2 & Jumper A2
¾
A single controller must be set to IPN network address 0 (zero). In a multi-controller system one controller must be set to
address 0 (zero) to serve as the master. The other controllers must be set to address 1-7 with no two controllers set the same.
The 1524 requires that a jumper be soldered across location A2 to select addresses 4 through 7.
IPN NETWORK ADDRESS
MASTER
SLAVES
DIP
SWITCH
0
1
2
3
4
5
6
7
JUMPER
(A2) NO NO NO NO YES YES YES YES
# 1 (A1)
OFF
OFF
ON
ON
OFF
OFF
ON
ON
# 2 (A0)
OFF
ON
OFF
ON
OFF
ON
OFF
ON
MOUNTING
¾
CAUTION:
Mount the 1524 vertically to promote air flow and do not enclose in a confined space. The 1524 is not watertight and
must be protected from rain, snow and excessive moisture. Do not to place mounting screws under large brown capacitor when
securing mounting box to surface. DO NOT remove from or install into mounting box with power applied as damage resulting from
shorting to the mounting box voids the limited warranty. An optional black powder coated deluxe mounting box available.
DETAILED DIMENSIONAL DRAWING
FIGURE 6
)