Work mode
7
Commissioning
7.6
93
7.6
Commissioning
WARNING
Risk of injury from moving components.
Movable parts can cause severest injuries during operation.
−
Do not stay in or close to danger zones.
−
Never reach into running devices.
−
In particular, never open the dome screen during operation.
−
Never take the safety switch, which protects against opening the dome
sieve during operation, out of operation.
−
Only carry out work when the dome screen is closed.
Checks before commissioning
The following basic checks must be carried out before each commissioning:
−
Is the machine installed correctly.
−
Is the machine secured against rolling away.
−
Does the ground have sufficient bearing capacity.
−
Are all safety and protective devices fitted and functional.
−
Is the machine technically in order.
−
Are all cables and connections connected and secured.
−
Are all machine closures closed (tank, oil, cooler, battery, filter, etc.).
−
Are all lubrication points greased sufficiently.
−
Is the central lubrication functioning properly.
−
Are the delivery hoses, couplings and seals in perfect condition.
−
Is the discharge stand mounted correctly.
−
Do delivery hoses and couplings match each other.
−
Are securing devices (hose holders, suspension eyes) for the laid
delivery hoses are in place. Are the delivery hoses and delivery hose
connections adequately secured.
−
Have the delivery hoses been laid correctly (see Section 7.4).
Summary of Contents for alpha CR
Page 6: ...Contents ...
Page 180: ...14 Appendix 14 1 Declaration of conformity 180 14 1 Declaration of conformity ...
Page 181: ...Appendix 14 Drawings 14 2 181 14 2 Drawings 14 2 1 BMS alpha CR standard ...
Page 182: ...14 Appendix 14 2 Drawings 182 14 2 2 BMS alpha CR B feeder ...
Page 183: ...Appendix 14 Drawings 14 2 183 14 2 3 BMS alpha CR B S feeder scraper ...
Page 185: ...Appendix 14 Circuit diagrams 14 3 185 ...
Page 186: ...14 Appendix 14 3 Circuit diagrams 186 ...