8
Cleaning
8.5
Cleaning the machine
120
8.5
Cleaning the machine
If work is interrupted for a longer period of time or at the end of work, the
mixing and delivery vessels and the delivery hoses must be emptied and
cleaned.
At the end of work, the machine must also be cleaned completely and the
lubrication points greased according to the lubrication schedule.
8.5.1
Cleaning the vessel ventilation unit
At the end of work and during longer interruptions and if necessary during
work, the vessel ventilation unit must be cleaned.
1.
Switch the machine off via the "Control unit on" switch.
2.
Secure the machine against restarting To do this, disconnect a battery
contact.
Figure 61: Cleaning the vessel ventilation unit
3.
Fold the vessel vent (1) backwards as far as it will go.
4.
Open the dome cover (see Section 7.7.6).
5.
Rinse the air vent (3) and the sealing cone (2) with plenty of water.
6.
Mechanically loosen stuck material residues with a scraper or similar.
➢
Take care not to damage the sealing cone (2).
7.
If there is material residue in the air duct of the dome cover, close the
dome cover (see Section 7.7.2).
8.
Loosen the cover screws and pull the cover out.
9.
Remove the material residues from the air duct with water or
mechanically with a scraper.
10. After cleaning, screw the cover to the dome cover.
11. Close the dome cover if necessary (see Section 7.7.2).
Summary of Contents for alpha CR
Page 6: ...Contents ...
Page 180: ...14 Appendix 14 1 Declaration of conformity 180 14 1 Declaration of conformity ...
Page 181: ...Appendix 14 Drawings 14 2 181 14 2 Drawings 14 2 1 BMS alpha CR standard ...
Page 182: ...14 Appendix 14 2 Drawings 182 14 2 2 BMS alpha CR B feeder ...
Page 183: ...Appendix 14 Drawings 14 2 183 14 2 3 BMS alpha CR B S feeder scraper ...
Page 185: ...Appendix 14 Circuit diagrams 14 3 185 ...
Page 186: ...14 Appendix 14 3 Circuit diagrams 186 ...