Safety
2
Security risks
2.8
23
2.8.4
Risks from electrical current
Touching live parts can lead to serious injury or even death. For this reason,
work on electrical equipment may only be carried out by qualified
electricians.
Before starting any work on electrical equipment, disconnect the machine
from the power supply and check that it is voltage-free. Secure the power
supply against being switched on again.
Check the electrical equipment regularly for external damage (e.g. to the
insulation) and loose connections at cable terminals. If defects are detected,
switch off the voltage supply immediately and arrange for repair.
The electrical equipment (e.g. also cables and plugs) must not come into
contact with water.
Only use undamaged extension cables that are suitable for use in the
respective environment and whose core cross-section is sufficiently
dimensioned.
Do not bridge or disable fuses. When replacing defective fuses, always
make sure that the current is correct.
2.8.5
Risks due to hazardous substances
Health hazards can occur with incorrect handling of auxiliary and working
materials (oils, greases, etc.). Observe the operating material notes in the
safety data sheets of the manufacturer.
Always wear the necessary personal protective equipment when handling
auxiliary and operating materials. When refilling, use devices that prevent
splashing and spilling.
Dispose of used auxiliary and operating materials in accordance with the
local, nationally applicable legal regulations.
Water-polluting substances such as e.g. greases, lubricating oils or solvent-
containing cleansing liquid and the like must not pollute the ground or get
into the sewer system. These substances must be collected, stored,
transported and disposed of in suitable containers.
2.8.6
Risks from pressure vessels
The mixing and delivery vessel is a pressure vessel. It is subject to the
pressure vessel regulation §8 group IV.
The required pressure vessel test was carried out by the manufacturer. An
acceptance test of the system is required before the first commissioning (§9)
and at regular intervals (§10). The tests are carried out by an approved
testing centre.
Summary of Contents for alpha CR
Page 6: ...Contents ...
Page 180: ...14 Appendix 14 1 Declaration of conformity 180 14 1 Declaration of conformity ...
Page 181: ...Appendix 14 Drawings 14 2 181 14 2 Drawings 14 2 1 BMS alpha CR standard ...
Page 182: ...14 Appendix 14 2 Drawings 182 14 2 2 BMS alpha CR B feeder ...
Page 183: ...Appendix 14 Drawings 14 2 183 14 2 3 BMS alpha CR B S feeder scraper ...
Page 185: ...Appendix 14 Circuit diagrams 14 3 185 ...
Page 186: ...14 Appendix 14 3 Circuit diagrams 186 ...