I
NSTALLATION
,
O
PERATION
&
M
AINTENANCE
Commissioning
C
OMMISSIONING
C
HECK
L
IST
You must complete, date and sign the ‘tick box’ checklist in the owner’s
warranty card. Use this copy to check the installation prior to completing the
owner’s documentation.
Unit
All equipment ordered by the
customer is installed.
The unit is level and secure.
The water supply line has been
flushed to clear swarf and debris and
is free of leaks.
The tank is free of foreign matter and
debris and the water isolating tap is
turned ON.
Water drainpipe work is completed
and sealed.
The water basin fills with water and
the float valve closes correctly when
the water level is 65 -70mm from the
bottom of the tank.
The water pump(s) operates correctly
when turned ON at the controller.
The Dialflo water bleed rate is
adjusted to suit local water
conditions.
The Dump Valve (option). The tank
drains correctly when unit turns off.
The fan deck is correctly located and
the fan blade spins freely.
The mains and control wiring are
complete and the circuit breaker is
turned ON.
The fan operates correctly on all
speeds.
Water distribution is even with the
filter pads fitted and the air
conditioner operating pump and fan.
All Controller functions for the
appliance operate.
Fan motor current draw.
Ductwork and general
All ductwork is completed to plan,
correctly supported and airtight.
Air distribution checked, dampers are
adjusted and all outlets correctly
adjusted and wiped clean.
All roof penetrations are fully sealed
and watertight.
Man-hole cover replaced.
Site
All rubbish has been removed from
inside and on the roof.
Customer Hand Over
You have explained the following to the
customer.
The operation of the Controller.
Adequate exhaust is required for the
effective cooling. Air exit areas
should be at least 0.5 square meters
per 1000 litres of air.
The operation of the bleed or
dumping system and it’s importance
to operate all the time
Maintenance requirements
Page 18