Page:
35
OIM - Manual
Version:
2014/11
Speedlane 900
Edition:
SL900 -OIM - USA
6
Electrical wiring
Most wiring will come factory installed, only the external wiring and wiring between the master and
slave will need to be connected on site.
Mentioned wiring is a general overview.
Please refer to project specific electrical drawings.
6.1 Wiring between the Master and Slave unit
The following cables run between the master and slave unit.
All cables are supplied from the factory.
1. Motor cable
(4 x 0.75mm2 or 4 x 18 gauge)
2. Multi-beam cable
(5 x 0.5mm2 or 8 x 20 gauge)
Multi beam for High model
(5 x 0.5mm2 or 8 x 20 gauge)
3. Master
– Slave connection
(21 x 0.5mm2 or 21 x 20 gauge)
- Motor encoder
- Authorization LED
-
Traffic LED’s
6.2 External wiring connection
1. Mains power.
2. Fire alarm contact.
3. Access control.
- Authorization pulse in and out.
- Return signals in and out.
- Alarm contacts.
4. Control panel.
6.3 Wire connection locations
6.3.1 Internal
Motor cable.
The motor in the slave unit will need to be connected directly to the frequency controller in the
master unit.
Multi-beam.
The multi-beam cable runs from the master unit to the slave unit.
With a high unit the cables will be marked with 1 and 2 and need to be connected to the
corresponding multi-beam transmitter.
Master
– Slave connection.
The master
– slave connection cable runs from the master unit to the slave unit.
It is connected to the terminal strip in the slave, wire number 1 to terminal 1, wire 2 to 2, etc.