Now is the best time to install your roll-up sides. Doing
this now will help pull down the plastic tight before the
wiggle wire is installed on the hip-boards. This will
ensure even venting when the hand crank is used.
Connect ¾
″
EMT conduit along the length of each
side of the greenhouse, using ¾" couplings to connect
the pieces together. Extend the EMT a foot past the
edge of the greenhouse on both sides. If you are
using our ¾
″
couplings, using self-taping screws to
secure the poles together. If you are using a standard
EMT coupling make the screws as tight as you can to
prevent slippage. Roll the ends of the plastic around
the connected EMT until the greenhouse plastic is tight
and the pole is flush with the bottom of the
greenhouse.
Install snap clamps every 2 ft to ensure even
ventilation. After all the snap clamps are secure, the
greenhouse plastic should be hanging down taught.