Borg & Overström
GB
11
Install & Operation Manual
Undercounter Installation & Water Connection
*Sparkling versions only.
1
2
7
8
9
10
11
Locate the machine in a
suitable enclosure, ensuring
that the supplied ventilation kit
can be installed.
Connect the u1 tap to the
water outlet.
Connect the faucet connection
harness to the tap control
panel membrane.
*Connect the CO2 supply
from gas regulator, ensuring
the pressure is set to max 58
PSI (4 bar), and turn on the
supply.
Connect the chiller to the
water supply and open the
mains supply isolation valve.
Connect the unit to the
electrical supply and turn on.
After approximately 10
minutes, the compressor and
fan will stop as the chiller has
reached its normal operating
temperature.
*The carbonator should be
purged of air by activating the
sparkling water dispense for
approximately 20 seconds.
*Isolate the water supply
and activate the sparkling
water dispense. When the
water system has emptied,
allow gas to be expelled for
approximately 5 seconds.
Immediately after this 5
second period restore the
water supply and allow the
system to refill.
Dispense ambient, still and
sparkling water, in turn,
to purge any air from the
system. The time to do this
may vary depending on the
length of pipe between the
unit and the tap.
3
6
5
10
mins
58 PSI
20
secs
Install within connection box
as supplied.
4