Issue/Amendment
Page
Bosch BPT-S String Inverters
1.4
3/4
From
Quick Installation Manual
Our Reference
Date
BPTE/SA
M1-AO
Matthew
Argyropoulos
Dec 4th, 2015
2
Starting up the inverter
Follow sequence below:
1.
Turn
DC Isolator
to ON Position
2.
Turn
AC Solar Switch
to ON position
3.
Turn
Inverter
ON using the Service switch at the
bottom of the unit (from 0 -> 1)
e.Key or Hand Operated
should appear on the screen
Note:
Follow the sequence in reverse to shut down the inverter.
3
Commissioning with e.Key
Hold the e.Key next to the specified point on the inverter – see
picture.
To setup the time and date see section
5
.
4
Hand operated commissioning
IMPORTANT: IF A WRONG PARAMETER IS CHOSEN DURING MANUAL
COMMISIONING RESTART THE INVERTER. THIS QUICK FIX APPLIES FOR THE
LANGUAGE AND COUNTRY SELECTION. IF YOU COMPLETE THE SETUP A
LAPTOP/ SMARTPHONE WILL BE REQUIRED TO RESET THE UNIT.
Use long and short gestures to setup the Language, Country and Grid connection
parameters loaded on the inverter.
-
Hold
your hand in front of the inverter until the
progress bar on the screen is full.
-
Language
selection is first. English should be shown
already. If another language is present
wave
your
hand in front of the inverter screen until English is
shown.
-
Hold
your hand in front of the inverter until the
progress bar on the screen is full to lock the language
setting.
-
Country
is next. Australia should be shown already.
If another country is present
wave
your hand in front of the inverter screen until
Australia is shown.
-
Hold
your hand in front of the inverter until the progress bar on the screen is full to lock
country setting.