Commissioning (contractors only)
4
Commissioning (contractors only)
For correct commissioning, it is essential that the
following steps are carried out in the order
shown.
1. Set the DIP switch on IPM 1 and IPM 2 in
accordance with the details in the instructions
supplied.
2. Switch the system ON.
3. Program additional room temperature
controllers FR 10 (not permissible in
Germany) or FR 100 in accordance with the
details in the manual supplied.
4. When commissioning for the first time or after
a complete reset (all settings have been
reset), you need to select the display
language:
–
Turn
to select the language and press
to confirm. (For how to change the
language
Æ
chapter 6.4.4 on page 49.)
5. If the power reserve has run out, set the time
and date as follows:
–
Turn
to select the hour and press
to confirm.
–
Turn
to select the minutes and press
to confirm.
–
Turn
to select the year and press
to confirm.
–
Turn
to select the month and press
to confirm.
–
Turn
to select the day and press
to confirm. (For how to change the date
and time
Æ
chapter 6.4.1 on page 49.)
6. Set the code for the heating circuit (only
FR 100 with BUS connection)
–
If the controller is to control heating circuit
HC
1
and DHW heating:
Identification CH
circuit
select code 1 with
and
confirm with
.
–
If the controller is to control heating circuit
HC
2...10
:
Identification CH circuit
with
select
a code between 2 and 10and confirm with
.
7. During commissioning, automatic system
configuration starts immediately after entry of
the date and time.
–
Wait for 60 seconds and then follow the
instructions displayed.
–
If automatic system configuration does not
start of its own accord, start it from the
menu
Æ
chapter 8.2 on page 58.
8. Switch off automatic
Auto switch between
GMT - BST
Æ
chapter 6.4.1 from page 49
9. Adjust other settings to suit the current
system,
Æ
chapter 6 starting on page 30 and
chapter 8 starting on page 54.
10. Fill and vent the solar thermal system
according to its documentation and prepare it
for commissioning as described in chapter 8.4
on page 60.
11. Adjust other settings to suit the current solar
thermal system,
Æ
chapter 8.5 starting on
page 60.
12. Commission the solar thermal system,
Æ
chapter 8.5.1 on page 61.
The functions of the controls and
the meanings of the symbols on the
display are explained on pages 2
and 3.
Only one FR 100 or FR 10 can be
assigned per heating circuit and per
code (not permissible in Germany).