8
Commissioning and validation
8.1
Initial commissioning
Step
Relevant chapters and literature
Set the address.
chapter 5.1.3 "Setting DIP switch" on page 23
.
Install the module in the IndraControl S20 station.
Application description of the IndraControl S20 system
)
Connect the lines for the bus system and the supply voltag‐
es to the IndraControl S20 station.
Application description of the IndraControl S20 system
or the documentation of the bus coupler
).
Wire the outputs according to your application.
chapter 7 "Connection examples of the safe out‐
.
Before applying the operating voltage:
●
Ensure that there are no wiring errors (e.g. cross-fault
or short circuit) or grounding errors using a multimeter.
●
Ensure that the functional earthing is connected.
Connect the required voltages to the IndraControl S20 mod‐
ule.
Application description of the IndraControl S20 system
or the documentation of the bus coupler.
Connect the required voltages (U
O
) to the module.
After applying the operating voltage:
●
If possible, measure the ripple of the voltages to en‐
sure that there are no deviations.
●
Measure the input voltages at the module to ensure
that they are within the valid range.
●
Check whether the module starts without errors using
the LEDs on the module.
Check the mounting and installation.
For the checklist, refer to
chapter 14 "Checklists" on page
Make the required parameterizations.
For the module parameterization, refer to
eterizing the module" on page 29
.
Program the safety function.
User manuals of the function blocks used.
Perform a function test and the validation. Check whether
the safety function responds as planned during programming
and parameterization.
For the checklist, refer to
chapter 14.5 "Validation" on page
Check whether the module started correctly and whether er‐
rors are displayed when adding the supply voltages using
the diagnostic and status displays.
For the procedure when an error is pending, refer to
9 "Errors: Reporting and troubleshooting" on page 43
Tab. 8-1:
Commissioning steps
DOK-CONTRL-S20*SSDO*8*-AP02-EN-P
Bosch Rexroth AG
41/85
IndraControl S20 Module With Safe Digital Outputs S20-SSDO-8/3
Commissioning and validation