Automatic configuration of the tightening channel
Automatic initial
commissioning
Automatic commissioning is active if there is no existing channel configuration. Here, the components
recognized by the tightening controller are transferred to the channel configuration without querying the
user and configured with a default value (SE, IM, LTU).
The PLC assignment table is generated automatically. To call up the configuration of the tightening
channel, select
System
Tightening channel configuration
or .
Automatic channel
configuration
Automatic channel configuration is active if the
Automatic
option is selected under
Channel
in the global
parameters (see
). Automatic channel configuration allows for example
to replace the ErgoSpin during operation (plug & run). The ErgoSpin data are then transferred to the
channel configuration without querying the user. All other components must be manually configured.
7.7.3.3
SE/CS PLC assignment table
Control unit (SE)
The PLC assignment table defines the assignment of the control signals to the tightening controller's
physical interfaces of the tightening controller (Arcnet, fast inputs/outputs, module slots) of the
SE352(M).
Programming the IM24V interface module in the type B1/B2 slot
Load the assignment table via
System
SE/CS PLC assignment table
.
To ensure simple program selection, assign the signals in the
Inputs
group as follows:
•
Prog0 to B1/B2 0.0
•
Prog1 to B1/B2 0.1
Send the changed PLC assignment table to the SE.
To initialize other processes with the tightening sequence evaluation, assign the signals in the
Outputs
group as follows:
•
Ok
to B1/B2 0.0
•
Nok
to B1/B2 0.1
Compact system (CS)
The assignment is largely specified for the compact system and does not need to be changed for basic
commissioning. You can, however, optionally specify the input signal for the tool button on the hand-held
nutrunner.
For this, proceed as follows:
1.
Load the assignment table via
System
SE/CS PLC assignment table
.
2.
Click the
ErgoSpin 0.3
input.
3.
Click
<<
to remove the existing signal.
4.
Click the desired input signal (e.g.
ResRs
).
5.
Click the
ErgoSpin 0.3
input.
6.
Click
>>
to assign the signal.
The ResRs signal is displayed for the
ErgoSpin 0.3
input (see Figure
Automatic commissioning can be forced during later operation by simultaneously deleting the channel
configuration and PLC assignment table.
In doing so, the output drive components for the ESV and ESM are deleted automatically.
The PLC assignment table is generated automatically during automatic commissioning.
For information on offline configuration, see chapter
Summary of Contents for Rexroth Tightening System 350
Page 4: ...4 641 Bosch Rexroth AG Schraubtechnik System 350 3 608 878 300 2019 03 ...
Page 120: ...120 641 Bosch Rexroth AG Tightening Technology 3 608 878 300 System 350 3 608 878 300 2019 03 ...
Page 194: ...194 641 Bosch Rexroth AG Tightening Technology 3 608 878 300 System 350 3 608 878 300 2019 03 ...
Page 638: ...638 641 Bosch Rexroth AG Tightening Technology 3 608 878 300 System 350 3 608 878 300 2019 03 ...