3.0

    THE QUICK START MENU 100 TO SET CT AND VT RATIOS

 

 

The 100 Menu allows you to set the CT ratio- voltage measurement values, target power factor setting., 

and switching time per step.  This is the menu the Commissioning Engineer can use on site. Other settings 
in the expert menus can be made with the help of a qualified Engineer or Technician.

Values of kW/kVA/kvar will not be correct unless the correct setting is made for voltage 

(Un) and current. (Ct)
In order to make these settings we have to go into the commissioning menu 100.

How to get into menu 100:

press 

 repeatedly to get back to the value 0....i 

Now press 

 and you see 'INFO' in the top right corner

Press 

 again and you see 'MANUAL'

Press 

 again and you see 'SETUP'

Press 

 and release .'100' shows in the display

Press 

 again – you are now in the commissioning menu 100. The 100 menu allows you to make the 

essential settings are marked in 

bold

Un – Voltage Setting 

The first value you see is the Un. This is the 

phase – phase voltage., not Phase-Neutral. 

So for the UK for 

example the setting for Un is 415v. This is the factory default setting for relays made in the UK after serial 

number 1123596
If you need to change this press 

 and the first digit starts flashing – using 

adjust as needed and key 

 to 

adjust the second figure and so on. Press 

 to confirm and the digits stop flashing. 

It is important to have the correct voltage setting Un because the alarm thresholds are defaulted to operate 

when the voltage is +-10% from nominal Un setting.

C.T Setting 

To set the CT ratio key 

 and the first digit starts flashing.

Assume the CT ratio is 1000/5., which is 200/1. Always set the CT ratio as a multiplication factor to 1 so for 

the CT ratio 1000/5 we set Ct to 200. The same sequence with 

 and 

 is used for all the other settings.

Pt – Voltage Transformer ratio setting

This is only used when the relay is used on MV/HV systems. The default setting is 1., but if the relay is 
working on an 11kv system with 110v voltage input ., the setting for Pt is 100

Ai – Automatic Initialisation

This is defaulted to NO and we recommend it is left on NO

If set to 'YES' – when the relay is first commissioned it will switch each step one by one. It will correct any 
mistaken wiring of the CT.., and store the kavar values per step in its menu. We do not recommend use of 

this Ai feature unless you do not know which phase the CT is on. 
If Ai is ‘NO’ then no automatic switching on initial energising will take place, and the steps will be switched 

in for the first time when they are required. Each time they switch their kvar value is recorded in the micro-
processor memory.

PFC – Step switching Control

This control allows you to decide how you want the steps to be switched. The possible selections are :

ON -     Normal switching of steps on/off as the reactive demand changes. This is the normal AUTO control
OFF –   Reactive control de-activated and all steps in circuit will be switched off

HOLD – The steps switched in will remain on. The reactive control is de-activated
The default setting is 'ON'- automatic switching of steps.

Page 6 of 11

Summary of Contents for CXPLUSR

Page 1: ... Page 4 2 1 Lockout time 75 secs 2 2 Measured Values in the Display Scroll through Menu What do the symbols mean Page 5 3 0 THE QUICK START MENU 100 TO SET CT AND VT RATIOS How to get into Setup Menu 100 Page 6 Setting the nominal system Voltage L L Un Setting the CT ratio Ct Setting the VT ratio Pt Selecting Automatic Self Commissioning Ai Selecting AUTO OFF HOLD for all the steps Page 7 Setting ...

Page 2: ... capacitor current b The ratio of the CT is such that full load current is about 75 of the CT ratio e g for a Max load of 500 amps select a CT ratio of 800 5 not 5000 5 This is because at the lower current ranges C T s are less accurate c Do not use a CT with too low a ratio for the measured load e g If the load is 750 Amps and you use a 500 5 CT the CT will then be saturated and will give inaccur...

Page 3: ...1 6 Wiring diagram 1 6 1 CXPLUS R Contactor switching Page 3 of 11 ...

Page 4: ...art menu 2 2 Measured Values in the Display The three larger digits at the top show system 50 hz power factor e g 0 91i lagging p f 0 91 0 98c leading p f 0 98 If you have a known lagging power inductive load then i should be displayed in the LCD If you see c and you are certain the load is lagging switch off and swap over Um1 and Um2 This is better than swapping over a load carrying CT which may ...

Page 5: ...e is above 5 check the current taken by the capacitors since high THDU can result in harmonic overload of the capacitor steps Harmonic Blocking reactors must then be fitted to limit harmonic overload current 3 5 7 9 11 13 15 17 19 harmonic voltages as of fundamental 0 i cos Top figure Fundamental 50 60hz Cosphi to 2 decimal places Bottom figure Fundamental Cosphi to three decimal places as require...

Page 6: ...lted to operate when the voltage is 10 from nominal Un setting C T Setting To set the CT ratio key and the first digit starts flashing Assume the CT ratio is 1000 5 which is 200 1 Always set the CT ratio as a multiplication factor to 1 so for the CT ratio 1000 5 we set Ct to 200 The same sequence with and is used for all the other settings Pt Voltage Transformer ratio setting This is only used whe...

Page 7: ...ontact can be used to start up the ventilation fan If you select AL for one of the exit relays the default switching temperature is 30ºC when this contact will close FOFF This step is permanently off Fixed off FON this step is permanently on Fixed on Default setting is AUTO 4 0 MANUAL SWITCHING 4 1 Sometimes there is no load on the system when the relay is commissioned In order to test everything ...

Page 8: ...ltage outside tolerance set in menu 204 thi The second ambient temp set in menu 514 has been exceeded Sequential switching off of steps to bring ambient temp down will commence I Lo Measured current below 15mA Check for open circuit or short circuited CT or insufficient load OPH The limit set for operating hours between servicing has been reached Call the service engr I Hi Measured current too hig...

Page 9: ...ct time delay of THDU alarm 506 NO Freeze exits if no CT current 300 CONTROL 507 YES YES Service alarm operates when max operating hours or switchings on any step is reached 301 60 value of kvar for step switching 508 80 000 Set No of contactor operations for Alarm 302 1 00 Target PF 1 509 9 000 Set No of operating Hours for Alarm 303 0 95i Target PF 2 510 NO Temperature sensor is set to monitor t...

Page 10: ... above 5 amps Check the CT ratio selected Change if necessary Display shows PFC ALARM Continuous over compensation or continuous under compensation Check the capacitors and contactors Contactor could be welded in Check that steps are not in the FON setting PFC Out in menu 100 Is the kvar supplied sufficient for the reactive demand If not under compensation will be reported Display Shows Leading Co...

Page 11: ...he exit relays as ventilation fan contact Data Output BSTO software by TTL on back of relay Operating Temperature 20 70ºC Storage 40 85ºC Humidity 0 95 Dew droplets not permitted Over Voltage Category II Pollution Degree 3 DIN VDE 0110 Part 1 IEC 60664 1 Standards Complied with DIN VDE 0110 part 1 IEC 60664 1 1992 VDE 0411 part 1 DIN EN 61010 1 IEC 61010 1 2001 VDE 0843 Part 20 DIN EN 61326 IEC 61...

Reviews: