05
-
2015 Rev.1
6.
44
Parte 6 Utilizzo
6.1 INTRODUCTION BEFORE EVERY USE
6.1.a
Danger of crushing –
collision and abrasion
The operator in charge of using the Platform must be informed about the safety instruc-
tions shown in this manual (see Part 2) and must wear work gloves and safety shoes.
6.1.b
Before and after every use at the beginning of every moving the operator
must always
carry out:
The pre
-
start inspection (6.2) –
Functioning test (6.3).
6.2
PRE
-
START INSPECTION
6.2.a
Make sure that all manuals are in the suitable containers on the Platform board.
6.2.b
Make sure that the marking of the Platform and all safety labels are in their place per-
fectly integral and readable.
6.2.c
Check the Platform to verify the absence of anomalies (example: cracks on the weld-
ings, missing or loosing bolts, different dents, buckling, etc.), malfunction or non author-
ized variations (example: non authorized lifted flatcar) depending on how the Platform
has been delivered by the Manufacturer.
6.2.d
Check the integrity of the basket and the right functioning of the entrance (automatic
lock).
6.2.e
Check and test the functioning of all the safety devices (
Q3
and
P6
Stop/Emergency
buttons, flashing, safety bar, microswitch, tilt device, pot hole devices).
6.2.f
Check the functioning of the key switch
Q2
.
6.2.g
Check and test the functioning of the safety manual lowering lever
6.2.h
Check the water level in the batteries, make sure there are no leaks. Cables must be
constantly right fixed to the clamps; there must be no corrosion.
6.2.i
Check that the rubber wheel has not any damage, abrasion or deep cuts and that there
are no rubbish on the wheels or around them.
6.2.l
Check the basket extension system.
6.2.m
Check that there are no leak of oil.
6.2.n
Check that the hydraulic oil is at level, in case fill to the correct level (see Part 9 Mainte-
nance).
6.2.o
In case you will find one or more anomalies is forbidden to use the Platform, so do all
the necessary before starting to use it (see Part 9 Maintenance).
6.2.p
The pre
-
starting inspection procedure is finished.
Proceed with the working test.
04
-
2020 Rev.01
P
ART 6 OPERATIONS