C - VACUUM / HYDROSTATIC FILLING
F
IELD
A
IR
I
NTEGRITY
I
NSPECTION
T
EST
:
YOUR PRODUCT WARRANTY WILL BE VOID IF YOU DO NOT
Hold pressure
for a
minimum of 1 hour for a Field Integrity Inspection Test.
After passing
the pressure test, it is HIGHLY RECOMMENDED that the 4 PSI is
maintained for as long as possible, up until the time of backfill.
YOUR PRODUCT WARRANTY WILL BE REVOKED IF YOU
CHOOSE TO SKIP THE AIR INTEGRITY TEST OUTLINED IN YOUR
COPY OF YOUR PRODUCT INSTALLATION INSTRUCTIONS. YOU
MUST
COMPLETE THE
PRESSURE TEST PRIOR TO HYDROSTATIC FILLING OF THE SUMPS.
The Bravo Double Wall product’s ship from the factory with a combination gauge factory- installed
and held under 20” of mercury / vacuum.
C.1 -
After passing the Field Air Integrity Test
per the Installation Instructions and there are no
signs of leaks, you must cut the permanently affixed pipe plug from the tubing connected to the side
wall. This is NOT the tubing with the gauge connected to it.
C.2 -
Connect (newly cut) open end of tubing
to barb-and-ball-valve assembly.
(sold seperately)
A 36” length of clear tubing
is factory installed to the barb-and-ball-valve assembly.
After the penetration
fittings have been
installed, the vacuum has
been lost. Pressure/soap
tests should have been
conducted prior to filling
the sumps with liquid.
Barb & Ball Valve
Assembly
Cut Plug end off
from tubing
Connect
Assembly to
tubing
You must cut off the barbed
plug and connect the
provided Barb & Ball Valve
Assembly. Close off the ball
valve and prepare the
Venturi Vacuum Generator
and air supply to be used to
fill Sump with liquid.
7
ii-B409-DW-10A