REFRESH
INSTALLATION, OPERATION AND MAINTENANCE MANUAL
Assembly, Installation and Commissioning
2.4
Commissioning
2.4.1
Pre-commissioning Procedures
2.4.1.1 PPE
Suitable protective clothing.
2.4.1.2 Refresh Control Panel
Once all of the wiring has been completed and tested, the system is ready to be commissioned.
Refer to Section 2.4.2 below.
2.4.2
Commissioning Procedures
2.4.2.1 Setting up the Filter Lifetime Monitoring
Note: The following procedures apply to the Refresh Ultima only.
Filter Life Expectancies
This will vary depending upon the establishment. For this reason the life expectancies can be
reprogrammed to suit. However, the pre-set default times will be as per the maintenance table for
“
Medium category establishments
” unless Britannia Kitchen Ventilation has been instructed to
provide a different setup (in writing and prior to delivery). Refer to
.
Step 1:
To access the filter stage reset panel, open the hinged access panels at the lower front
of the Services Tower.
Filter stage reset panel
Step 2:
Using the DIL switches 1, 2, 3 & 4 (toggle switches) on the front of the filter stage reset
panel; the lifetime of the filters (in hours) can be set. Refer to the following table of filter
lifetimes for Stages 2, 3, 4 & 5:
Issue: Final
Page 25 of 70