G730-Install-IG100 Installation Guide
Brocade
®
G730 Switch Hardware Installation Guide
Figure 34: Installing SFP-DD Transceivers
1. SFP-DD Transceiver
2. Pull Tab of Transceiver in Lower Row
3. Dust Caps
4. Pull Tab of Transceiver in Upper Row
4. Remove the first dust cap from the transceiver. Leave the second dust cap in place.
5. Position a cable so that the molded grid pattern and wide key tab on one side of the cable connector are facing up
(away from the transceiver pull tab).
If you are inserting the cable into a transceiver on the lower row of ports, the molded grid pattern on the cable should
be facing down (away from the transceiver pull tab).
Figure 35: Orientation of the SFP-DD Connector
G730-Install-IG100
58
Summary of Contents for Brocade G730
Page 94: ......