Micro 70 Wire Guidance Important Information
PS
S8.0
8200
F-code
Section
C-code
Version no
T-code
001
OE35
© BT Products
293
Service Manual
1997-10-24
Micro 70 Wire Guidance Important
Information
1. Powering Up:
Installed at customer location
1. Disconnect battery from truck.
2. On the center relay move wire #84 from relay
terminal position #1 to relay terminal position #4.
3. Install 1A & 20A fuse in their proper position as
shown below. Wire #94 is on 1A fuse Wire #72 is
on 20A fuse
4. Connect battery to truck.
2. Powering Down:
Transporting the truck: (Not using an industrial battery)
1. Disconnect battery from truck.
2. Remove 1A & 20A fuse from holder.
3. On the center relay move wire #84 from relay
terminal position #4 to relay terminal position #1.
4. Connect temporary battery to truck.
This unit is shipped with the N.D.C.
Wire Guidance Controller disengaged to
prevent damage. The wire guidance
controller must NOT be engaged until
the trucks industrial battery is installed.
Failure to heed this instruction will result
in damage to the N.D.C. Controller and
void warranty.
CAUTION