3.5 - Checklist before start
42
TCT-2301 Installation instructions
M2007/3en
©BTG 2004
3.5 Checklist before start
When you are confident that your TCT-2301 has been correctly installed,
and are ready to power up the system for calibration and/or testing, run
through this brief check list before powering up. Using this list will help
ensure trouble-free initialization of your system.
1. Make a clear water adjustment before installing the probe in the
ball-valve arrangement. See TCT-2301 operating instructions,
section 4.2.
2. Check that the measuring gap on the probe is at the correct angle
to the pulp flow.
3. Check that the transmitter is fully inserted and the two security
screws are properly tightened.
4. Ensure that the optical fiber is protected from mechanical dam-
age, and attached securely to the transmitter.
5. Check all wiring.
6. Switch on the mains power supply.
7. Connect the hand-held terminal to the electronics box. Switch it
on and check that the display lights up.
Proceed to the TCT-2301 Operation instructions.