Check which main gas nozzles suit the mains gas
supply: Check for gas characteristics with your gas
supply company and observe the details in Table 11,
page 22 and Tab. 12.
!
Ensure that the designation of the main gas nozzles
(Fig. 6) correlates to Table 12), and convert to a
different gas type, if necessary (see "Converting the
boiler to a different gas type", page 48).
The following applies to Belgium (BE):
Only Buderus service engineers may carry out a
conversion to another gas type.
Fig. 6
Checking the main gas nozzle
Item 1:
Short version (natural gas L (G25), S (G25.1))
Item 2:
Long version (natural gas H (G20), GZ50 or LPG)
1
2
CAUTION!
SYSTEM DAMAGE
through incorrect main gas nozzles.
!
Only commission the gas burner with
correct main gas nozzles.
!
Ensure that the correct main gas
nozzles have been used.
!
If necessary, change the gas type see
Chapter 9 "Converting the boiler to a
different gas type", page 48.
Main gas nozzle designation
Natural gas
H (G20)
GZ 50
Natural gas
L (G25)
S (G25.1)
LPG
Propane
P (G31)
LPG
B/P (G30)
295
340
190
180
Tab. 12 Main gas nozzle designation
WARNING!
RISK TO LIFE
from risk of electric shock.
!
The installation, repairs, electrical
wiring, the initial start-up, the mains
electrical connection as well as
maintenance and service work must
only be carried out by a competent,
authorised specialist.
!
Ensure that, during any work of that
nature, all current technical rules and
local regulations are applied.