Boiler block assembly
8
Logano GE515 - We reserve the right to make any changes due to technical modifications.
25
z
Insert the anchor rods with fitted spring kits on the l.h.
and r.h. sides, on the top and bottom adjacent to the
boiler hubs, into the cast lugs (Fig. 22,
[1]
to
[4]
).
z
Tighten the nuts by hand.
z
Now tighten the nuts on each anchor rod by 1 to 1½
turns.
z
Align the boiler on the plinth or vibration absorbing
plinth in the horizontal and vertical plane
(
chapter 7 "Boiler positioning", page 14).
z
Remove the boiler compression tool.
Install the feed pipe in the next installation step
(
Æ
chapter 8.4 "Sliding the feed pipe into place (carton
of installation components)", page 27).
USER NOTE
z
Loosen the compression tool – but do
not remove - after the front section has
been assembled. First inset the anchor
rods.
Fig. 22 Install the anchor rods
2
1
3
4
CAUTION!
SYSTEM DAMAGE
through inadequate compression force.
z
Do not unwind the spring kit.
Use it only in its original state.