7
Commissioning
7.1
To be checked before commissioning
No.
Check
✓
1
All transport aids and assembly fixings have been removed.
2
The electrical installation has been carried out and checked by an
authorized, qualified electrician.
3
All electrical terminal boxes and sockets are closed.
4
The machine is grounded.
5
Direction of rotation of gearmotor is correct.
6
All bolted joints are tightened.
7
There are no foreign objects in the machine.
8
The gearmotor is filled with lubricant.
9
All piping connections are tight.
7.2
Inspection of EC conformity
Operate the machine in the European Union only if EC conformity has been
checked and confirmed using the following checklist.
No.
Check
✓
1
The operating company has been informed that the operating in-
structions must be accessible to personnel at all times.
2
The operating company has been informed that it is responsible
for instruction of personnel.
3
Assembly and installation have been carried out in accordance
with the operating instructions.
4
5
The machine is grounded via the motor protection conductor or
the connection labeled with the
symbol (equipotential bond-
ing). The paint coating has been removed in the area around the
ground connection.
6
The operating company has been informed that the items in the
operating instructions marked with the
symbol MUST be ob-
served for compliance with the ATEX certification. The ATEX ap-
proval ceases to apply if such points are not observed.
7
A lockable safety switch is present, and personnel have a match-
ing lock.
Bühler AG
MAYV-20150-2-1808-en-US
Chapter 7
Commissioning
19