TECHNICAL PASSPORT. INSTALLATION and OPERATION MANUAL
TECHNICAL PASSPORT. INSTALLATION and OPERATION MANUAL
7.2. Pellet boiler connection to the pellet
burner, auger and fuel hopper
- Take the auger hose (from the auger
set). Using a bracket, clamp one end of
the hose onto the motor-end outlet of
the pellet auger.
- Using a bracket, clamp other end onto
the feeding chute of burner
- Remember pellet auger must be installed
at 45° angle to the ground horizontal
surface.
- Fill the hopper with fuel (see table 2 for
parameters of the fuel types used)
- Plug the power cord of the pellet auger
into the indicated Schuko-type boiler
socket on the left side of the boiler
housing.
1. Pellet boiler PelleBurn;
2. Pellet burner Pell;
3. Auger hose;
4. Auger;
5. Fuel Hopper FH.
Diagram 6. Pellet burner Pell and Fuel Hopper
connected to pellet boiler PelleBurn
7.3. Connecting the boiler to the mains
power supply
Such connection must be
performed by a technician /
service shop authorized for such
operations.
Caution!
ELECTRIC
SHOCK
HAZARD!
- Before opening the unit: switch
off the voltage and secure the
unit against accidental restart.
- Observe installation instructions.
It is mandatory to assure a
backup power generator of
corresponding rated power! (see
table 1)
Improper cable connections may
damage the regulator!
The device may be damaged if
struck by a lightning. Make sure
it is unplugged during the storms.
To bring into exploitation the boiler and
auger must be connected to the electricity
network 220V/50Hz with power cord.
Create tight connection with the electrical
mains which complies with the local
regulations.