INSTRUCTIONS FOR THE INSTALLATION
CMC-030/CMV-030
1 : The supply voltage required for the unit and the pump is
120 VAC with a 20 A circuit
breaker.
2 : For a proper functioning of the machine, leave a 6’’ (15 cm.) minimum clear space around
the condenser to facilitate air flow.
3 : Install a tube of cooling line at the output of the pump.
4 : Install the return of the same line at the input of the tank (to create a closed circuit).
5 : Remove the cover of the unit and pour 1 gallon (1 X 4 liters) of glycol 100% in the tank for
the CMC-030 or 2 gallons (2 x 4 liters) for the CMV-030 and add water until just below the
overflow.
6 : Before plugging the pump
, ensure that the installation and connections have been made to
required specification. After any adjustments, plug in the pump.
Important:
Never operate the pump before filling the tank.
The pump must always run to have a constant agitation in the tank and avoid damaging the
compressor.
7 : The level of liquid in the tank will go down until the cooling line is filled.
8 : Add water until just below the overflow.
9 : Replace the cover on top of the unit.
10 : Switch on the unit. Note
there is a one minute delay before the unit start-up.
11 : The temperature will slowly drop until 28⁰F (factory setting) on the thermostat display.