BWT myPOOL
POOL’N BOX
1.4.2 Tools
Excluding the materials required for excavation and pouring the concrete slab, we recommend that you
have the following equipment on hand:
•
measuring tools: decameter, rope, big spirit level
•
mallet
•
percussion drill with concrete drill bit, diameter 10 mm
•
drills and drill bits, flat head screw diver, cross head screw driver, drill bit diameter 10 mm
•
cutting tools: Stanley knife, metal saw, hole saw diameter 60 mm
•
tube or socket wrench (13 and 17mm), set of Allen keys
•
finishing tools: sand paper, lime fine
1.4.3 Assembly time
Excavation and earthworks:
1 TO 2 DAYS DEPENDING ON THE MATERIALS USED
Metallic structure:
½ DAY (WITH 2 PEOPLE)
Pouring the slab:
½ DAY (WITH TWO PEOPLE) DEPENDING ON THE MATERIALS USED
Wooden structure:
1 DAY (WITH TWO PEOPLE - THE TIME INDICATED DOES NOT INCLUDE
THE CONCRETE CURING TIME)
Curing of the concrete slab:
21 DAYS (3 WEEKS)
CAUTION
O
nce the structure has been assembled, the liner must be fitted and the pool must be filled with water
within at most 5 days. Past this time limit, the structure will need to be carefully inspected to ensure
the absence of any deformations (movement of the slats, shrinkage, etc.) that could impact the
structural integrity of the work. In the event that gaps appear between the slats, refit them perfectly
before fitting the liner.