SBBI-2 MODE SELECTION

 

 

ACTION WHEN POWER FAILS: 
 

‘Single’ Gate System- 
 
‘Open’ Mode: 
Power failure is verified for about 10 seconds, inverter is started, gate(s) is commanded to open, after 
about 60 seconds inverter is stopped, and system waits for power restoration. After power is restoration, 
power is verified for about 10 seconds, a ‘cycle’ command is issued causing gates to operate to the 
closed position. 
 
‘Secure’ Mode: 
Power failure is verified for about 10 seconds, inverter is started and system waits for a power 
restoration. After power restoration, power is verified for about 10 seconds and inverter is stopped. 
 
‘Double’ Gate System 
 
‘Open’ Mode: 
Power failure is verified for about 10 seconds, inverter is started, first gate(s) is commanded to open, 
after about 60 seconds second gate(s) is commanded to open, after 60 seconds inverter is stopped, and 
system waits for power restoration. After power restoration, power is verified for about 10 seconds, a 
‘cycle’ command is issued causing gates to operate to the closed position. 
 

DIP SWITCH SELECTION

 

 

Position 1: 

Down- Selects ‘single’ gate system operation; SW 1 positions 2, 3, and 4 are active 
Up- Selects ‘double’ gate system SW 1 positions 2, 3, and 4 are not active 
 

Position 2: 

Down- Selects ‘open’ mode as the action upon power failure 
Up- Selects ’secure’ mode as the action upon power failure 
 

Position 3: 

Down- Selects opening action when battery exhausted in ‘secure’ mode 
Up- Selects remain ‘secure’ (closed) when battery exhausted 
 

Position 4: 

Down- Selects operation as defined by position 2 and 3 switches 
Up- when ‘secure’ mode selected, inverter runs for about 2 minutes only when an external 12v signal is 
applied to terminal 1 of TB3

Summary of Contents for SBBI-2

Page 1: ... the top of page 2 2 5 Foot Lead In Cables for Battery to Inverter Connection 100 Amp Fuse for Installation between Positive Battery Terminal and Inverter Fuse Holder Customer supplied Items Battery see page 3 for Selection Guidelines Battery Enclosure Weather Resistant Enclosure Connectors Commercial Power Input Wiring Installation and Wiring Instructions Inverter Installation 1 Unpack inverter f...

Page 2: ...gle phase commercial power to TB1 1 115VAC Hot Black 2 115VAC Neutral White 3 Earth Ground Green Device Control Functions Connect supplied function control wiring harness 18 6 cord to TB3 1 Remote control device 2 Motor 1 open contact 3 Motor 1 open common 4 Motor 1 cycle common 5 Motor 1 cycle contact 6 Motor 2 cycle contact 7 Motor 2 cycle common 8 Motor 2 open common 9 Motor 2 open contact 10 N...

Page 3: ... are shipped in a separate package Fuse is already installed on positive battery cable CAUTION Connect battery only after commercial power is connected and turned on to the device Connecting battery before commercial power is turned on could result in device moving and possibly injuring persons or causing damage to property Battery Selection Guidelines SBBI recommends 12VDC Maintenance Free sealed...

Page 4: ...inverter is started first gate s is commanded to open after about 60 seconds second gate s is commanded to open after 60 seconds inverter is stopped and system waits for power restoration After power restoration power is verified for about 10 seconds a cycle command is issued causing gates to operate to the closed position DIP SWITCH SELECTION Position 1 Down Selects single gate system operation S...

Page 5: ...e Byan Systems prewire 2 115VAC Hot Black 3 115VAC Neutral White 4 Earth Ground Green Gate Control Functions Connect supplied function control wiring harness to TB3 in a battery back up to accessory terminals on the G2M control board not installed in a Byan Systems prewire SBBI TB3 G2M Accessory Terminals 1 Empty Not Used 2 Black 18 master board 3 White 16 master board 4 Green jumper from 3 16 mas...