Installation
This chapter contains the detailed instructions for the module installation, from
the initial inspection phase to the first switch-on of the power unit.
2.1
Preparation for Use
Do not apply power before reading this chapter.
sequence of instructions to prepare the power supply for its use.
Step
Checklist
Description
1
Initial inspection
Physical inspection of the power supply
2
Mounting
Install the power supply, ensure proper ventilation
3
AC Input Power Connection
Connect the power supply to the AC source
4
Load connection
Wire size selection, remote sensing
[5]
Hydraulic Plugs Connection
Exclusively for water cooled models
6
Output Grounding
Grounding or floating output
7
First switch-on
Switch-on checkout procedure
Table 8:
Installation checklist
2.2
Initial Inspection
Prior to shipment, the power supply has been inspected and found free of
mechanical or electrical defects. Upon unpacking of the power supply, inspect for any
damage which may have occurred in transit.
The inspection should confirm that there is no exterior damage to the power
supply (e.g. broken switch or connectors) and that all the panels and the display are not
scratched or cracked. Keep all packing material until the inspection has been completed.
If a damage is detected, compile the RMA form (available to the CAEN ELS web site).