4. Then place the 1 covered platform
to the 3rd step. Balance the scaf-
fold according to the long sides and
short sides by using a water scale.
(Diagram 5) You need to turn the sc-
rewed tool on the wheels right and left
in order to balance your scaffold.
5. Fix 4 balance legs (support) to the
scaffold. Connect the connection tool
between the short part of the balance
legs to the gap between 2nd step and
3rd step and its long part to the gap
between 6th step and 7th step. Af-
ter making sure the tools completely
grasp the carrier profile, tighten the
bakalite heads by turning. Make sure
each balance leg wedges are in conta-
ct with the solid surface (Diagram 6
and 7). It is not mandatory to use ba-
lance legs for working heights lower
than 2.5 m. However if the work app-
lies a horizontal load on the scaffold,
balance legs should be used.
6. Go on top of the platform of the 3rd
step. Place the modular frames of
the 2nd floor by passing through
the modular frames of the 1st floor.
Pass the security pins from the holes
of the modular frames and lock it.
(Diagram 8)
5
6
7
8
11
EN