1. Introduction
This assembly and usage hand book is pre-
pared with for the usage of Professional
Aluminum Scaffolds (Narrow-Wide-Fol-
ding) which will be referred to as ProTU-
BE Scaffolds together its configuration.
Before starting to the assembly of ProTU-
BE Scaffolds carefully read these instru-
ctions. The required scaffold should be
assembled and used in accordance with
these instructions.
All instructions in this handbook must be
exactly complied with.
In case of failure to comply with the ins-
tructions of this handbook an accident
may occur. Çağsan Merdiven shall not
be responsible for assembly and usage
of ProTUBE Scaffolds manufactured by
Çağsan Merdiven Company in violation
to this handbook.
Employer, supervisor and user shall be
responsible for the correct usage of the
scaffold in accordance with this handbo-
ok and to keep this handbook ready where
ProTUBE Scaffold is used.
2. General
For Standard ProTUBE Scaffold configu-
rations see the configurations table in this
handbook.
ProTUBE Scaffold can only be assemb-
led, disassembled or modified under the
supervision of an authorized person and
by people who are trained for the related
specific risks;
• Understanding of assembly, disas-
sembly or transformation plan of Pro-
TUBE Scaffolds;
• Assembly, disassembly or transfor-
mation of ProTUBE Scaffolds secu-
rely;
• Measures for prevention of risks
towards people or objects; Safety me-
asures for weather conditions which
may negatively affect security of the
ProTUBE Scaffolds
• Permitted load;
Other risks to occur as a result of abo-
ve mentioned assembly, disassembly or
transformation works.
The people who are responsible for the job
shall be able to reach this handbook.
Only original Çağsan Merdiven parts
should be used for assembly.
Standard Çağsan Merdiven - ProTUBE
Scaffold configurations meet the Europe-
an Standard EN1004.
Please take in consideration the national
or local regulations before use the wor-
king tower. If available and possible to
perform successfully the people working
on the fitting should be connected to the
outer wall for additional personal security.
People should not connect themselves to
the scaffold unless scaffold is fixed to the
wall.
2.1 Usage
Çağsan Merdiven ProTUBE Scaffolds
can be used in heights.
Max Platform Height
Product
Indoor
Outdoor
ProTUBE L
12,20 m.
4,63 m.
ProTUBE L
12,20 m.
8,00 m.
ProTUBE S
6,50 m.
6,50 m.
ProTUBE F
4,40 m.
4,40 m.
• Maximum load per platform is 1,50
kN/m
2
• EN 1004-2-4,63/12,20-XXXD (Pro-
TUBE L) (TUV-SUD Mark)
• EN 1004-2-8,00/12,20-XXXD (Pro-
TUBE L) (TSE Mark)
• The horizontal loads that result from
the works to be made on ProTUBE
Scaffolds and which exceed 30 kg
should not be permitted.
• If there are excessive winds, ProTU-
BE Scaffolds should be fixed.
• ProTUBE Scaffolds can only be used
on horizontal, straight and solid sur-
faces.
• ProTUBE Scaffolds should not be
used with wind speed more than 38
km/h (max. 6 Beaufort).