EVERSKY
™
MS-CDF-019
–
Manufacturing Nr: 22
0001→
Version B
Update: 2022/06/14
16/70
VIII.5.b.
Installation of the unit on its support
Step
Description
1
Place the unit in horizontal position (doors below and blowing grid at the front) and remove the transport supports.
2
Lift the unit and bring it close to its
final position about 80mm from the
wall and 80mm from the ceiling. (In
this step, the screws (E) are still set
back from above the unit)
3
Adjust the position of the unit
laterally using the 2 template plates
acting as visual guide/marker.
4
Raise the unit until it is flush with
the ceiling.
Engagement of threaded rods inside the unit
5
Move the unit backwards until it is
leaning against the wall.
6
Open the side doors to tighten the
nuts inside the unit so that the unit
can be placed correctly against the
ceiling and its trim adjusted.
7
Arrange the removable port / blind panels from inside according to the configuration of the installation (see I.5 Airflow
connections).