PH
-SERIES
13
9.0
ASSEMBLY OF COMPONENTS
WARNING:
SEE PAGE 20 FOR VENTILATION REQUIREMENTS FOR THIS HEATER. MAKE SURE YOU HAVE
THE CORRECT MODEL FOR THE INTENDED APPLICATION. IF IN DOUBT CONTACT THE FACTORY FOR
DETAILS PRIOR TO INSTALLATION OR OPERATION.
9.1
GENERAL INSTRUCTIONS
Refer to figures on page 11 to 15
Note: If unit is to be installed on a 25 degree tilt refer to page 11 for this type of installation.
1)
Measure and locate holes to be drilled for mounting brackets into overhead beams or
support. The PH-40, PH-40 HO and PH-75 HO have two (2) mounting locations, one at each
end. The PH-50, 75, and 80 have a third located in the center of the unit. The PH-100 has 4
and the PH-125 has 5.
2)
FOR RIDGID INSTALLATION: READ WARNING ON PAGE 9 FIRST.
When installing fasteners such as bolts, inserts, threaded rod, etc, it is suggested that the
fastener(s) are no less than 3/8 inch (.9525 cm) in diameter (two (2) per hanging point) and
must penetrate and be secured in the overhead material in such a way that the unit will not
be dislodged from the mounting location during normal use and operation, including wind
load. This is the responsibility of the installing contractor and if in doubt, they shall contact the
manufacturer of the fastener chosen to verify its use.
(See WARNING on page 9)
3)
Lift and support preassembled unit in a safe manner, and locate where heater is to be installed.
Install fasteners through hanging brackets (optional) into the mounting material (beam, support
etc.). Then attach heater to the brackets. PH-40, 40 HO & 75 HO are now mounted. In the case
of the PH-50 & 75, the last section will have to be installed to the mounted, preassembled, first
10’. (see item #5)
4)
CHAIN INSTALLATION: DO NOT USE IN WINDY CONDITIONS - READ WARNING ON PAGE 9
FIRST.
Adequately secure hanging chains as mentioned in the above item #2. Drop chains to desired
elevation and attach heater to them utilizing two lengths per hanging point.
5)
PH-50 & 75: Unassembled parts. Secure end cap to one end of the reflector by over lapping
reflector onto end cap % inch, (1.905 cm) (see page 13) and secure via self tapping screws.
6)
Attach the reflector assembly to the 10’ (3m) section already mounted by overlapping the
opposite reflector end onto the hanger assembly by % inch. (1.905 cm). Secure hanger on end
cap end via fasteners into the previously drilled holes located in the beam, support etc. Secure
opposite end of reflector to hanger via self tapping screws.
7)
Install radiant tube by positioning three (3) inch (7.62 cm) end into end cap from below, and
butting the other end to the previously installed section. Secure clamp with self tapping
screws (see figure 9 page 13). For PH-
50 tube slides over the first 10’ (3m) section tube. Secure
with screws.
8)
Install decorative grille (2 -
5’ (1.53m) pieces) onto lip of ref
lector in a similar fashion used to
install 2x4 ceiling panels. If need be, remove some of the screws securing the reflector to the
hanger and/or end cap, spread reflector to facilitate installation, being careful not to damage