Chapter 5: Installation
203
PMP 4 50 AP
1
Fasten an AWG 10 (or 6mm
2
) copper ground
cable to each ODU grounding point using the
M6 (small) lugs
2
Tighten the Ground post locking nut in the
copper wire
3 Securely connect the copper wire to the grounding system (Protective
Earth) according to applicable regulations.
PMP 4 50 SM
1
Fasten an AWG 10 (or 6mm
2
) copper ground
cable to each ODU grounding point using the
M6 (small) lugs
2
Tighten the Ground post locking nut in the
copper wire
3 Securely connect the copper wire to the grounding system (Protective
Earth) according to applicable regulations.
The grounding point on PMP 450 Series SM 900 MHz is different from 2.4, 3.5/3.65 and 5 GHz PMP 450
SMs as shown in PMP 450 900 MHz SM grounding.
Summary of Contents for PMP 450 Series
Page 92: ...Chapter 2 System hardware 92 Figure 29 MicroPoP Omni antenna implementation pattern Vertical...
Page 134: ...Chapter 3 System planning 134 Figure 51 Mast or tower installation...
Page 135: ...Chapter 3 System planning 135 Figure 52 Wall installation...
Page 136: ...Chapter 3 System planning 136 Figure 53 Roof installation...
Page 137: ...Chapter 3 System planning 137 Figure 54 GPS receiver wall installation...
Page 158: ...Chapter 3 System planning 158 Figure 61 cnMedusa Antenna...