Applies to IRFU deployments only.
This section describes how to install an IRFU with antenna and waveguide.
Install the antenna and flexible waveguide by following their manufacturers’ instructions.
The waveguide must be long enough to connect to the IRFU branching unit in its rack.
Preparation
Before installing the IRFU, ensure the following are provided:
•
IF cable for CMU and IRFU (Cambium part number 30009403001).
•
A -48 V dc
power source.
•
Access to the building ground terminal.
•
All required tools (
Ta ble 2 1 6
Tools r equired for I RFU inst allat ion
I t e m
Re qu ir e d spe cifica t ion s
W h e r e u se d
Screwdriver
Phillips #2, medium tip
Throughout
Allen key
For #8-32 socket-head
screws
For connecting the flexible
waveguide to the IRFU
Multimeter
With ohm meter
For connecting the CMU to
the IRFU
Miscellaneous tools for
installing connectors on
the CMU to IRFU
coaxial cable
Refer to the manufacturer
documentation provided with
the connector
Torque wrench for SMA
connectors
5/16, set to 0.1 kg•m
(9.0 lb-inch)
Summary of Contents for PTP 800 Series
Page 1: ...Cambium PTP 800 Series User Guide System Release 800 05 02 ...
Page 40: ...Licensing requirements About This User Guide 10 phn 2513_004v000 Oct 2012 ...
Page 232: ...Limit of liability Chapter 3 Legal information 3 22 phn 2513_004v000 Oct 2012 ...
Page 322: ...Radiation hazard assessm ent Chapter 4 Reference information 4 90 phn 2513_004v000 Oct 2012 ...
Page 428: ...Replacing IRFU components Chapter 5 Installation 5 106 phn 2513_004v000 Oct 2012 ...
Page 630: ...Using recovery mode Chapter 7 Operation 7 78 phn 2513_004v000 Oct 2012 ...