Task 15: Connect ing link t o t he net work
Chapt er 6: Configurat ion and alignm ent
6- 114
phn- 2513_004v000 ( Oct 2012)
Task 15: Connecting link to the network
Perform this task to connect to the network and set the system clock.
This task consists of the following procedures:
•
•
on page
•
Saving the system configuration
Connecting to the network
To complete and test the network connections, proceed as follows:
1
Disconnect the local PC from the CMU management port at each CMU.
2
Connect the CMUs to the network equipment using the cables that were
prepared in
Preparing network connections (1+0 and 2+0 links)
Preparing network connections (1+1 Hot Standby)
3
Check that each of the CMUs is reachable from the network management
system by opening the web interface to the management agents, or by
requesting ICMP echo response packets using the Ping application. The
network management system will normally be geographically remote from the
site, so it may be necessary to request that this action is completed by co-
workers at the management centre. Alternatively, it may be possible to use
remote login to the management system.
For testing the remote end of a link with in-band management, the wireless
link may need to be operational first.
4
Check that the data network operates correctly across the wireless link. This
may be by requesting ICMP echo response packets between hosts in the
connected network segments, or by some more structured use of network
testing tools.
5
For a 1+1 Hot Standby link:
Initiate a protection switch at one end of the link (as described in
) and check that the data network operates
correctly across the wireless link (as described in the previous step).
Initiate a switch back to the primary unit.
Repeat for the other end of the link.
Summary of Contents for PTP 800 Series
Page 1: ...Cambium PTP 800 Series User Guide System Release 800 05 02 ...
Page 40: ...Licensing requirements About This User Guide 10 phn 2513_004v000 Oct 2012 ...
Page 232: ...Limit of liability Chapter 3 Legal information 3 22 phn 2513_004v000 Oct 2012 ...
Page 322: ...Radiation hazard assessm ent Chapter 4 Reference information 4 90 phn 2513_004v000 Oct 2012 ...
Page 428: ...Replacing IRFU components Chapter 5 Installation 5 106 phn 2513_004v000 Oct 2012 ...
Page 630: ...Using recovery mode Chapter 7 Operation 7 78 phn 2513_004v000 Oct 2012 ...