T107 Weather Station
User supplies valve box at base of station and weatherproof
enclosure for transformer. See FIGURE 2-1.
The AC power supply option at one time included a step-down
transformer instead of the power supply. Appendix E provides
information about using the step-down transformer.
2.1 Base Foundation
2.1.1 Supplied Components
(3) 5/8 inch Anchor L-Bolts
(9) 5/8 inch Nuts
(1) Anchor Template
Refer to Section 1,
Preparation and Siting
, for components supplied by
installer and bring components.
2.1.2 Installation
1.
The ET Tower attaches to a user supplied concrete foundation constructed
as shown in FIGURE 2-2.
2.
Construct the concrete form with 2 inch x 4 inch lumber and 16p nails.
3.
Assemble the template and anchor bolts. There should be two nuts below
and one nut above the template on each bolt.
4.
Clear an area large enough to set the form at the desired elevation.
5.
Dig a hole 2 feet x 2 feet x 2 feet. Lighter soils may require a deeper hole.
About 20 inches below the top of the hole, gouge a small cavity in one
wall of the hole. The cavity should be about 4 inches deep and just large
enough in diameter to insert one end of the conduit. Make certain the
cavity “points” in the direction from which power and communications
cables will come. For example the cavity will “point” towards a valve box
if one is being used.
6.
Center the form over the hole. Adjacent to the form, drive four stakes into
the soil. Secure the leveled form to the stakes with the 8p nails.
7.
Cap the ends of the conduit with duct tape. Position the conduit and wire
into place by securing the wire to nails in the form.
8.
Fill the hole and form with approximately 1/2 yard of concrete. Screed the
concrete level with the top of the form. Center the template assembly over
the conduit and press into the concrete. Put 2 x 4 spacers between the
template and the top of the form. The bottom of the bolt threads should be
about 1/2 inch above the concrete. The template must be level in two
dimensions. Use a trowel and edger to finish.
9.
Wait 24 hours before removing the concrete form. Wait 7 days before
mounting the ET Tower.
NOTE
NOTE
11
Summary of Contents for T107
Page 2: ......
Page 3: ......
Page 49: ...T107 Weather Station FIGURE 2 31 Slide Antenna Bracket U Bolt around Back of the Pole 41...
Page 78: ...T107 Weather Station 70...
Page 93: ...Appendix C Exploded Views C 1 Enclosure C 1...
Page 94: ...Appendix C Exploded Views C 2 Crossarm C 2...
Page 102: ...Appendix D Default Programs D 8...
Page 105: ......