This  appliance  uses  a  single  cylindrical  burner  installed 
horizontally  into  the  cavity  located  in  the  center  of  the  heat 
exchanger.  A  unique  burner  is  used  for  each  one  of  the 
DynaMax HS models.  

Burners may NOT be interchanged between different Btu/hr 
input  models.  The  burner  consists  of  a  round  mounting 
flange  welded  to  a  ported  stainless  steel  mixing  tube.  This 
stainless  steel  tube  is  covered  with  a  close  fitting,  knitted 
stainless steel metal fiber alloy material that forms the burner 
outer  surface.  The  burner  is  setup  to  operate  in  blue  mode 
and infrared operating condition should be avoided. Infrared 
operation will occur only if air to gas adjustments is incorrect. 
If infrared operation is noted the cause must be corrected. 

The  burner  should  be  removed  for  inspection  and  cleaning 
on  an  annual  basis.  An  appliance  installed  in  a  dust  or  dirt 
contaminated  environment  will  require  inspection  and 
cleaning  on  a  more  frequent  schedule.  The  fan  assisted 
combustion  process  may  force  airborne  dust  and  dirt 
contaminants,  contained  in  the  combustion  air,  into  the 
burner. 

With 

sustained 

operation, 

non-combustible 

contaminants  may  reduce  burner  surface  area,  reduce 
burner  input  or  cause  non-warrantable  damage  to  the 
burner.  

Airborne  contaminants  such  as  dust,  dirt,  concrete  dust  or 
dry  wall  dust  can  be  drawn  into  the  burner  with  the 
combustion air and block  the burner  surface area. DO NOT 
operate this appliance during construction. 

The  spark  igniter  and flame  sensor are  removable  from  the 
combustion  chamber  mounting  door  without  removing  the 
burner assembly. 

Never  use  an  open  flame  (match,  lighter,  etc.)  to  check 
gas connections.  

 

Regulated Gas Supply Pressures for DynaMax HS 
Boilers & Water Heaters

 

A  stable  gas  supply  pressure  is  important  to  avoid  rough 
starts with machines like the DynaMax HS which use a 1 to 
1 ratio control valve for internal gas pressure regulation.  
Camus  requires  that  all  DynaMax  HS  models  be  supplied 
with no more than 14” w.c. supply pressure. This means that 
lockup pressure must not exceed 14” w.c. 
 
A suitable lockup regulator with internal or external relief will 
not exceed running pressure by more than 20%. 
 
When required a final stage gas regulator is to be located as 
close  as  possible  but  no  more  than  10  feet  from  the 
appliance. 

It is paramount that maximum lockup pressure be confirmed 
before any attempt is made to start up the appliance. 
 
Operating  the  DynaMax  HS  at  lockup  pressures  exceeding 
14”  w.c.  could  lead  to  delayed  ignitions  and  damage  to  the 
appliance. 

 

 

 

 

PART 4 

WATER CONNECTION  

 

Check  all  applicable  local  heating,  plumbing  and 
building safety codes before proceeding. 

 

If the appliance is installed above radiation level it must 
be provided with a low water cut-off device at the time of 
appliance  installation  (available  from  Camus).  Some 
local codes require the installation of a low water cut-off 
on all systems. 

 

Before  connecting  DynaMax  HS  to  piping  in  a  closed 
loop  system,  flush  system  thoroughly  and  refill  with 
clean  water  and  add  chemical  treatment  to  bring  into 
balance. 

 

Follow  the  chemical  suppliers  instructions.  A  regular 
maintenance schedule will ensure that acceptable water 
quality  is maintained, typically a Langlier/ Reznor  index 
will provide this information. 

 

Strainers  are  recommended  to  be  installed  into  the 
system to prevent foreign objects from entering the heat 
exchanger. 

 

A  pressure  relief  valve  is  supplied  with  each  DynaMax 
HS.  The  relief  valve  must  be  mounted  in  a  vertical 
position and piped to the floor in a manner acceptable to 
the enforcing authority. 

 

Be  sure  to  provide  unions  and  gate  valves  at  inlet  and 
outlet  to  the  appliance  so  that  it  can  be  easily  isolated 
for service.  

 

On  combination  heaters  a  flow  setter  valve  at  the 
appliance  outlet  facilitates  setting  of  the  desired  outlet 
temperature at high fire. Refer to Section 10.9 Domestic 
Hot Water with Plate Heat Exchanger for more details 

 

This appliance is a low mass stainless steel tube design 
which  provides  for  instant  heat  transfer.  All  appliances 
are  supplied  with  an  internal  suitable  specific  pump 
mounted  in  place.  When  replacing  the  pump,  replace 
with one of equal or better-performance. 

 

An air vent is supplied on the heat exchanger header to 
eliminate  trapped  air.  Install  venting  devices  at  high 
points  in  the  system  as  well  to  eliminate  trapped  air  in 
the piping.  

 

Use suitable pipe hangers or floor stands to support the 
weight of all water and gas piping. 

 

The  DynaMax  HS  must  be  installed  so  that  the  gas 
ignition  system  components  are  protected  from  water 
(dripping,  spraying,  rain,  etc.)  during  appliance 
operation  and  service  (circulator  replacement,  control 
replacement, etc.)  

4.1 

FREEZE PROTECTION OUTDOOR 
INSTALLATION 

 

Appliance  installations  are  not  recommended  outdoors 
or  in  areas  where  danger  of  freezing  exists  unless 
precautions  are  taken.  Maintaining  a  mixture  of  70% 
water and 30% propylene glycol is the preferred method 
of  freeze  protection  in  hydronic  systems.  DO  NOT 
exceed a mixture  of 50/50. This mixture will  protect the 
appliance  to  approximately  -35ºF  (-37ºC).  Follow  the 
chemical suppliers directions. 

 

For  outdoor  installations  a  snow  screen  should  be 
installed  to  prevent  snow  and  ice  accumulation  around 
the  appliance.  Regular  inspections  should  be  made  to 
ensure  that  air  inlet  and  vent are free  of  snow  and  ice. 
Always  consider  the  use  of  a shelter such  as a  garden 
shed  in  lieu  of  direct  exposure  of  the  appliance  to  the 
elements.  The  additional  protection  afforded  by  the 

Summary of Contents for DynaMax DMH081

Page 1: ...mage personal injury or death Do not store or use gasoline or other flammable vapours and liquids in the vicinity of this or any other appliance WHAT TO DO IF YOU SMELL GAS o Do not try to light any a...

Page 2: ......

Page 3: ...NATION AND AIR INLET CLEARANCES 10 2 5 1 Sidewall Venting 10 2 5 2 Sidewall Air Inlet 10 2 5 3 Sidewall Concentric Vent Air 11 2 6 Vertical Direct Venting 11 PART 3 GAS CONNECTION 13 3 1 GAS CONNECTIO...

Page 4: ...NANCE 51 9 1 EXAMINE THE VENTING SYSTEM 51 9 2 VISUALLY CHECK MAIN BURNER FLAMES 51 9 3 CLEANING BOILER HEAT EXCHANGER 51 9 4 CONDENSATE TREATMENT 52 9 5 IGNITER AND FLAME SENSOR ELECTRODES 52 9 6 CHE...

Page 5: ...0 12 LOCAL REMOTE SWITCH 59 10 13 MODBUS LOCAL SWITCH 59 10 14 APPLIANCE 59 PART 13 PIPING DIAGRAMS 60 PART 14 EXPLODED VIEW PARTS LIST 65 PART 15 ELECTRICAL DIAGRAMS 73 15 1 DM 80 299 INTERNAL WIRING...

Page 6: ...QUENCE OF OPERATION 1 Power switch is placed in the ON position 2 Minimum 120 VAC 60Hz single phase 15A circuit is supplied to the DynaMax HS field connection board 3 24Vac power is supplied to the Dy...

Page 7: ...bustion and proper venting 1 6 INSTALLATION CODES The equipment shall be installed in accordance with those installation regulations enforced in the local area where the installation is to be made The...

Page 8: ...pecting and cleaning the heat exchanger and vent pipe 1 Turn off electrical power and main manual gas shut off and allow appliance to cool down 2 Remove the vent pipe at connection to heat exchanger a...

Page 9: ...ndoors where it is protected from exposure to wind rain and weather The appliance designed for outdoor installation Outdoor Models must be installed outdoors Always consider the use of a shelter such...

Page 10: ...ifications Model Depth Dim A in Dim B in Equivalent Length of Vent Air Intake Pipes at Recommended Diameter in Water Connection at Boiler in NPT Gas Connection at Boiler in NPT Over 25 and up to 100 O...

Page 11: ...t Recommended Diameter in Water Conn at Heater in NPT Gas Conn at Boiler in NPT Category IV CAT II Comb Vents Over 25 and up to 100 Over 15 and up to 25 Up to 15 210 36 22 3 4 14 1 4 23 24 1 4 34 1 4...

Page 12: ...7 Figure 5 DynaMax HS Wall Hung Service Clearances Figure 6 DynaMax HS Floor Mount Service Clearances...

Page 13: ...tive vent system is disconnected for any reason the flue must be reassembled and resealed according to the vent manufacturer s instructions Do not use an existing chimney as a raceway if another appli...

Page 14: ...onal designer acceptable to the authority having jurisdiction 1 The DynaMax HS Floor Mount boiler may be vented as a Category II appliance using sealed vent suitable for a condensing appliance 2 3 1 A...

Page 15: ...nterline radius 4 Vent outlet shall terminate at least 12 0 30m away from any forced air inlet Vent must be at least 7 feet 2 15m above grade when located adjacent to public walkways due to normal for...

Page 16: ...dence 7 Position termination so they are not likely to be damaged by foreign objects or exposed to a build up of debris 8 Flue gas condensate can freeze on exterior walls or on the vent cap Frozen con...

Page 17: ...Concentric Vent Vertical Venting CAUTION Do not operate appliance with the terminal cap removed as this may result in the recirculation of flue products Water may also flow into the combustion air pip...

Page 18: ...the size of the connection on the appliance Sizing based on Table 8 is recommended depending on model Before operating the appliance the complete gas train and all connections must be tested using so...

Page 19: ...ess The valve is a 1 1 negative pressure gas valve The valve performs the functions of a pressure regulator safety shutoff and air gas ratio control Full closing of the valve seat occurs in less than...

Page 20: ...If the appliance is installed above radiation level it must be provided with a low water cut off device at the time of appliance installation available from Camus Some local codes require the install...

Page 21: ...ntable heat exchanger damage Table 10 Minimal System Pipe Size Input BTU hr Water Size NPT in 80 000 1 100 000 1 150 000 1 199 000 1 1 4 250 000 1 1 4 299 000 1 1 2 399 000 2 500 000 2 600 000 2 700 0...

Page 22: ...99 000 12 6 7 2 10 8 5 8 250 000 15 8 11 5 13 5 8 7 299 000 18 9 9 3 16 2 7 0 399 000 25 2 8 4 21 6 6 3 500 000 31 5 9 2 27 0 6 9 600 000 38 8 17 5 32 0 11 8 700 000 45 3 18 2 40 0 14 4 800 000 51 8 2...

Page 23: ...ted every six months The normally open switch contact of the low water cutoff is to be wired in series with the flow switch This can be wired into the DynaMax HS terminal labelled Flow Switch CAUTION...

Page 24: ...be horizontal for at least an inch to ensure sufficient electrical conductivity 5 2 HIGH LIMIT A manual reset fail safe high limit aqua stat control is inside the appliance and the control bulb is in...

Page 25: ...utdoor sensor fault 105 Flame detected out of sequence 106 Flame lost in Main Flame Establishing Period MFEP 107 Flame lost early in run 108 Flame lost in run 109 Ignition failed 112 Pilot test flame...

Page 26: ...ay between stages minimum on time per stage minimum off time per stage Flame failure signal Error message display in text Manual override of boiler input rate for combustion Pump exercising feature ru...

Page 27: ...shooting information on the diagnostic screen Figure 25 Diagnostic Screen PARAMETER DESCRIPTION Boiler pump Pump A Auxilary Pump Pump B 3 way valve diverter operation DHW Pump Pump C Additional contac...

Page 28: ...int Modulates on boiler inlet sensor default Heat demand is generated when Remote Operator is closed 1 Place both toggle switches to LOCAL 2 Press and select Login 3 Select Quick Start 4 Select CH Set...

Page 29: ...switches to LOCAL 2 Press and select Login 3 Select Advanced Setup 4 Select CH Config 5 Select Outdoor Reset Config 6 Select Outdoor Reset and Press and select Enable 7 Set Max outdoor temp Warm weath...

Page 30: ...Connect Outdoor Sensor to J3 ECOM connector 4 Place both toggle switches in LOCAL 5 Press and select Login 6 Select Advanced Setup 7 Select CH Config 8 Select Outdoor Reset Config 9 Select Outdoor Res...

Page 31: ...structions Boiler operates with variable setpoint determined by 4 20mA incoming signal Modulates on header sensor Heat demand is generated when Remote Operator is closed and 4 20mA or 0 10Vdc signal i...

Page 32: ...CAL 2 Press and select Login 3 Select Advanced Setup 4 Select DHW Config Inlet Sensor operation 5 Select Demand switch Sensor only and Press 6 Select Mod sensor Inlet and Press go to step 7 DHW Stat o...

Page 33: ...eat demand is generated when Remote Operator is closed DHW Sensor Stat if required 1 Place both toggle switches in LOCAL 2 Press and select Login 3 Select Advanced Setup 4 Select DHW Config 5 Select D...

Page 34: ...address 1 7 Verify MB2 Modbus address 1 8 Select Lead Lag Config 9 Select Lead Lag Master Config 10 Select Master enable Enable Fixed Setpoint operation 11 Select Setpoint and enter desired setpoint u...

Page 35: ...ches in LOCAL 2 Press and select Login 3 Select Advanced Setup 4 Select System 5 Select System ID Access 6 Select MB1 Modbus address 2 To be in sequential order 7 Select MB2 Modbus address 2 To be in...

Page 36: ...mp src and Press 6 Select S5 and Press Master Boiler 7 Place both toggle switches in LOCAL 8 Press and select Login 9 Select Advanced Setup 10 Select Lead Lag Config 11 Select Lead Lag Outdoor Reset 1...

Page 37: ...t after Interstage delay 2 minutes a lag boiler will be brought online and will also fire at the base load rate specified Modulation of boilers will only occur after all boilers in the Lead Lag system...

Page 38: ...1 equalize run time default Add stage error threshold 718 0 130 o C Default 5 o F 3 o C Add stage inter stage delay 722 0 64800 seconds Default 120 seconds Drop stage threshold 727 0 130 o C Default 5...

Page 39: ...23 3 233 0 17 8 178 10 12 2 122 20 6 7 67 30 1 1 11 40 4 4 44 50 10 0 100 60 15 6 156 70 21 1 211 80 26 7 267 90 32 2 322 100 37 8 378 110 43 3 433 120 48 9 489 130 54 4 544 140 60 0 600 150 65 6 656...

Page 40: ...n LOCAL 2 Press and select Login 3 Select Advanced Setup 4 Select Burner Control Ignition 5 Select Adjustable lightoff rate and enter desired lightoff rate using 5 way control and press Adjust stack l...

Page 41: ...iption Programming Instructions To view burner run time pump cycles for maintenance and service purposes 1 Place both toggle switches in LOCAL 2 Press and select Login 3 Select Advanced Setup 4 Select...

Page 42: ...e deposit on the sensor rod must be removed with steel wool DO NOT use sand paper or grit cloth since this will contaminate the metal surface 7 3 COMBUSTION AIR FAN DynaMax HS uses a modulating air fa...

Page 43: ...from the system Verify that wiring is correct Flame Failure Pressing the manual OK button on the DynaMax HS Control Panel to restart the ignition sequence The boiler has failed to ignite the burner af...

Page 44: ...ocedure Clean or replace the burner if required Air in the piping system Purge all air from the piping system Incorrect igniter gap Check that spark gap is 9 64 Auto Reset High Limit Trips The outlet...

Page 45: ...are wired correctly Measure the resistance of the sensors 10k sensors Replace the sensor if necessary Fan Not Turning Fan refuses to rotate Alert 122 123 128 129 130 131 132 Check fan power wires Fan...

Page 46: ...Burner switch turned OFF 30 Burner switch turned ON 47 Flame rod to ground leakage 49 Abnormal 24Vac voltage 50 Modulation Fault 61 Anti short Cycle 62 Fan speed not proved 67 Interlock Off safety cir...

Page 47: ...turn at a time NO Verify gas valve is being powered by ignition control Check ignition speed is between 2500 to 3000 RPM using System Monitor NO Adjust ignition speed to 3000 RPM YES YES Burner light...

Page 48: ...tripped optional To identify the safety that is open set the multimeter to Vac and measure the voltage from one contact to ground The contacts produce a 24Vac when the circuit is closed Is vent and o...

Page 49: ...closed Is pump powered NO Check pump wiring and pump delay relay YES Is there a current transformer NO Check operation of paddle style flow switch installed on outlet of DynaMax HS YES Use meter to v...

Page 50: ...150 o F is selected and PVC venting is used the setpoint must be reduced to below 150 o F to avoid nuisance flame failures If a setpoint greater than 150 o F is required venting with CPVC AL29 4C 316...

Page 51: ...rod Is Flame sensor plug secure NO Fasten flame sensor plug securely to flame sensor wire and check for corrosion deposits at wire terminals YES Check continuity of flame sensor wire from flame sensor...

Page 52: ...x HS must be firing before proceeding DM 080 250 260 Figure 56 Venturi Gas Valve Assembly To adjust the high fire setting 1 Press the button 2 Select Test and press 3 Select Forced Rate and press 4 Se...

Page 53: ...1 Press the button 2 Select Test and press 3 Select Forced Rate and press 4 Select Set High Fire Locate the input adjustment screw on the top side of the gas valve Turn the screw 1 8 turn in either w...

Page 54: ...uction of air flow to the burner Yellow Flames Yellow flames can be caused by blockage of primary air flow to the burner or excessive gas input This condition MUST be corrected immediately If improper...

Page 55: ...eplace neutralizer medium as required There are several factors affecting amount of condensation created by the appliance however for rough approximation use Condensation Volume US Gallon Hr Input MBH...

Page 56: ...re when removing and handling the burner Sharp objects or impact may damage or tear the metal fiber surface rendering the burner unfit for service 9 8 REMOVAL OF COMBUSTION CHAMBER LINING The combusti...

Page 57: ...an be provided by using hydronic system antifreeze Follow the manufacturer s instructions DO NOT use undiluted or automotive type antifreeze Shut down and draining If for any reason the unit is to be...

Page 58: ...used The expansion tank must be installed close to the boiler and on the suction side of the system pump appliance Inlet to ensure proper operation Caution This appliance should not be operated at les...

Page 59: ...y loop 2 Check system for any water leaks 3 Check system for installation of glycol or water treatment where required Where glycol has been used to maintain the temperature rise across the appliance c...

Page 60: ...se 4 Be sure all valves are open between the hot water heater and the storage tank Ensure that all ball valves are fully ported 5 Check the pump to be sure it is running properly and that the pump mot...

Page 61: ...emain the same Lead lag Lead lag setpoint Add stage Error threshold AND Lead lag Lead lag setpoint Drop stage Error threshold 3 A boiler should stop Lead lag Lead lag setpoint Drop stage Error thresho...

Page 62: ...Local Remote switch is independent of the 4 20mA 2 10Vdc signal 10 13 MODBUS LOCAL SWITCH The Modbus Local Switch mounted on the terminal board is designed to relay the signal to the boiler display lo...

Page 63: ...eader to minimize induced flow through zones 2 Separate boiler loop as shown is recommended for system piping greater than 50 equivalent feet Pressure Reducing Valve Pressure Gauge Ball Valve Air Sepa...

Page 64: ...Valve Air Separator Expansion Tank Zone Circulator Flow Check Valve DynaMax HS Boiler Temperature Pressure Gauge Drain Union Anti scald Mixing Valve Note 1 Size main header to minimize induced flow th...

Page 65: ...Separator Expansion Tank Zone Circulator Flow Check Valve DynaMax HS Boiler Temperature Pressure Gauge Drain Union Anti scald Mixing Valve Note 1 Size main header to minimize induced flow through zone...

Page 66: ...63 Figure 34 Single Boiler Hydronic Heating Direct Storage Tank Zoned Piping Arrangement Cold Water In DHW Sensor Union Direct DHW Tank Anti Scald Mixing Valve Cold Water In Hot Water Out...

Page 67: ...Flow Check Valve DynaMax HS Boiler Master M1 Temperature Pressure Gauge Drain Union DynaMax HS Boiler Slave S2 System Sensor Note 1 Size main header to minimize induced flow through zones 2 Location...

Page 68: ...65 PART 14 EXPLODED VIEW PARTS LIST DYNAMAX HS WALL HUNG...

Page 69: ...66 DYNAMAX HS FLOOR MOUNT...

Page 70: ...ge Nuts GM10 05 012 X 5 Igniter GM10 35 108 01 X X X X X X X X X X GM10 35 161 01 X X X 6 Flame Sensor GM10 35 109 01 X X X X X X X X X X GM10 35 162 00 X X X 7 Igniter Flame Sensor Screws GM10 05 020...

Page 71: ...X VCZND6100 U X VBN3EM3POX X X VBN3FP3POX X X X 18 High Limit TCL085A X TCL110A X 19 Turn Lock Wall Hung X Floor Mount X 20 Wall Mount Back Panel 14 5402 X X X 14 5402 250 X X 21 Wall Mount Front Bot...

Page 72: ...X 14 5505 60 75 X X X 43 Side Panel Right 14 5506 20 25 X X 14 5506 X X X 14 5506 60 75 X X X 44 Side Panel Left 14 5507 20 25 X X 14 5507 X X X 14 5507 60 75 X X X 45 Front Panel Bottom 14 5508 X X...

Page 73: ...ange with 3 Street Elbow 44 0009 X 4 Air Intake Box 14 5551 X X 5 Air Intake Box 14 5546 X 69 3 Air Intake Adapter 44 0010 X 4 Air Intake Adapter 14 5559 X X 5 Air Intake Adapter 14 5556 X 70 Condensa...

Page 74: ...X X X X 91 DynaMax HS Fan Discharge Orifice 14 0377 80 X X 14 0377 100 X 14 0377 250 X X 92 Expandable Air Inlet Adapter w o Pressure Test Point 14 0378 X X X X X 93 Expandable Air Inlet Adapter 1056...

Page 75: ...t Mixing Chamber Gasket 33 0036 X X X X X X X 33 0037 X X X X X X X X X 33 0038 X 33 0043 X X X 33 0057 X X X 106 Air Inlet Gasket 33 0069 X X X 107 Current Transformer Combination Models only RIBXRA...

Page 76: ...73 PART 15 ELECTRICAL DIAGRAMS 15 1 DM 80 299 INTERNAL WIRING DIAGRAM...

Page 77: ...74 15 2 DM 399 800 INTERNAL WIRING DIAGRAM...

Page 78: ...75...

Page 79: ...ough sequential Modbus addresses Connect the system sensor to the master boiler The master boiler will use the water temperature in the primary loop to control the operation of the lead lag setup If o...

Page 80: ...s C2 Vdc Display J4 2 3 DHW Pump 1 6hp 4 24Vac or 115Vac for pump contact 5 6 3 way diverter valve 7 Boiler pump contact 10 24Vac return 12 Ground J5 1 Interlock 2 Gas Valve contact J6 1 Blocked Flue...

Page 81: ...excluded however if caused by appliance operation at large changes exceeding 150 F between the water temperature at inlet and appliance temperature or operating at temperatures exceeding 210o F BURNE...

Page 82: ...uilt water heaters and heating boilers as well as a into every single unit For more information supplier of specialty HVAC products Our service line is open 24 hours 7 days a week on our innovative pr...

Reviews: