AdditionAl Assembly instructions 

for eArthquAke Protected (eP) rAcks

7

 

EP Rack Assembly (Continued):

 Install all back 

restraint rail(s) and cover(s). See Figure 6. If installing a 
rack to hold either a JC or XTJ battery system, the provided 
spacer block must be installed between the restraint rails and 
the frame. See Detail 3. Position front restraint rail and cover 
temporarily next to front support rail prior to installing cells. DJ 
Series battery racks to utilize lower set of restraint rail holes to 
avoid interference with the handles.

8

 

Cell Installation Procedure:

 If not instructed otherwise, 

install cells starting at the center of the bottom row and, 
working out to each end, leave a half inch space between 
cells. For EP racks, use spacers between cells as supplied. 

Do not use oil or grease as lubricants

. Instead a small 

amount of water or unscented talcum may be applied to the 
rail cover to help reduce friction. For rows having an odd 
number of batteries, the center of the first battery installed 
will match the center of the row. For rows having an even 
number of batteries, a cell space will coincide with the center 
of the row. 

Pay attention to polarities and terminal placement

Refer to the battery’s Installation and Operating Instruction 
manual for more details. All cells should be pushed back 
against back restraint rail and cover. Up to 1/8” gap between 
restraint rail and cells is acceptable. Repeat this procedure 
for remaining steps and tiers, working upward. See Figure 7.

Figure 7a. Cell Spacer Detail (L-Series)

Front Restraint Rail 

and Cover (loose)

Figure 7. Cell Installation

Battery Units

Back Restraint  

Rail to Frame  

Connection.  

See Detail 3.

Figure 6. Initial Step For EP Rack

Back Restraint 

Rail and Cover

Frame

Detail 3. Frame and Restraint Rail(s) 

(Reverse View)

3/8-16 Hex Bolt, 

Lock Washer and 

Serrated Nut

Back Restraint 

Rail and Cover

1/2” Spacer 

Block. Used for 

“J” Series Only